Skip to content- Van Buren Street from Butternut to 136th Avenue is closed.
- **Starting today, the intersection of 160th and Van Buren will be closed for pipe installation.**
- The intersection of 152nd and Van Buren was opened to traffic on Friday, May 22.
- The intersection closure of 160th and Van Buren is anticipated to last approximately two weeks.
- A second K&R crew will begin pipe installation east of 144th Avenue this week if groundwater conditions permit.
- Van Buren Street from US-31 to 120thAvenue is closed.
- Work on various pipe appurtenances and work inside the pipe will continue sporadically over the next several weeks.
- Road restoration east of US-31 is scheduled to begin this week.
- New Holland Street from 104thAvenue to 96th Avenue is closed.
- The 42″ transmission main has been returned to service.
- Work on various pipe appurtenances will continue next week with work generally progressing from south to north.