TUESDAY, MAY 26, 2026

  • Van Buren Street from Butternut to 136th Avenue is closed.
  • **Starting today, the intersection of 160th and Van Buren will be closed for pipe installation.**
  • The intersection of 152nd and Van Buren was opened to traffic on Friday, May 22.
  • The intersection closure of 160th and Van Buren is anticipated to last approximately two weeks.
  • A second K&R crew will begin pipe installation east of 144th Avenue this week if groundwater conditions permit.

 

  • Van Buren Street from US-31 to 120thAvenue is closed.
  • Work on various pipe appurtenances and work inside the pipe will continue sporadically over the next several weeks.
  • Road restoration east of US-31 is scheduled to begin this week.

 

  • New Holland Street from 104thAvenue to 96th Avenue is closed.
  • The 42″ transmission main has been returned to service.
  • Work on various pipe appurtenances will continue next week with work generally progressing from south to north.
Contact a Location
Learn About Us
View Our Services
Facebook-f Linkedin Youtube Instagram

© 2026 Prein&Newhof, All Rights Reserved

  • Plan Room
  • Lab Results
  • Construction Updates
  • Survey Request