TUESDAY, MAY 27, 2025
Work completed/in progress:
Masonry and conduit installation continued.
Drain and water lines were installed in the dry well.
Masonry work was completed.
Anticipated work activities for the coming week:
Precast concrete plank ceiling will be placed.