Last week:
- Ric-Man resumed pipe laying between Barry Street and Van Buren Street.
- Tree clearing for surge suppression improvements continued at the Wyoming Drinking Water Plant.
Coming up:
- K&R is planning to mobilize a second crew the week of November 3. The second crew will begin work east of US-31 on Van Buren Street. Pipe laying is scheduled to begin the week of November 10.
Closures:
- Van Buren Street from Butternut to 160th Avenue remains closed. K&R is planning to re-mobilize and resume pipe laying within this area the week of November 3.
- New Holland Street between 96th Avenue and 104th Avenue is tentatively scheduled to close on November 3 for the foreseeable future. The detour will be via Quincy Street.
- Van Buren Street from US-31 to 128th Avenue is scheduled to close on November 3. The detour will be via New Holland Street.