Progress Report:
Walls are being built! But in this case, they will lead to community connections! The contractors are busy building walls on both sides of Northland Drive to form the approaches to the tunnel under the road.
Upcoming Work:
Speaking of the tunnel, all things are in place to close Northland Drive from Cannonsburg Road to Belding Road starting around 7pm on Friday, September 25. The contractor plans to work around the clock until the tunnel is across Northland Drive and the road restored. The road will be open sometime on Sunday, October 4 (if not sooner!).