Work Completed this past week (Aug. 25-30)
- C1, began placing curb/driveways/sidewalk on 3rd Street.
- C1, began sanitary sewer install on 3rd Street.
- C1, retaining wall footing prepped for concrete.
- C3, installed irrigation conduit on 3rd Street East of Creek.
- C3, began sanitary sewer install on Front/Main St.
- C3, began placing street light bases along Front/Red Bud.
- Access to Phillip 66 gas station switched back to South Red Bud.
Work planned for this week (Sept. 1-6)
- C1, continue road building on Dewey West of Red Bud.
- C1, continue retaining wall install on Red Bud.
- C1, continue sanitary sewer install on 3rd Street West of Red Bud.
- C3, continue sanitary sewer install on Main Street.