Progress Report:
- Base course paving from the lift station thru Egypt Valley Avenue has been completed. Top course paving, the last 1.5″ of asphalt, will be done for the whole project at the end.
- Dean’s continues to replace the sewer and bypass pump existing sewer flows around the work area. Current progress is a few hundred feet west of Old Town Road.
- Dean’s continues to rebuild the road behind the sewer crew east of Egypt Valley Avenue.
Upcoming Work:
Pending weather delays, sewer work is expected to wrap up in early October with shoulder restoration completed by the second half of October.