As you can see, the contractor made great progress (mostly) as planned this week on the road project. Feel free to drive on the roads in phase 1 as needed. However, please avoid parking on the edges of the new pavement for the next week to allow the valley gutters time to cure. This will help avoid damaging this part of the pavement.
The contractors ran into some unforeseen conditions on Grouse Ct. that have delayed that part of the project as well as the final top course of asphalt to the east of Grouse Ct. The contractors will be back next Monday to remove driveways and start milling the pavement in phase 2. The work on Grouse Ct. is still being scheduled. Stay tuned for further updates. Thank you for your continued patience.