Progress Report:
K&R continues to install 24-inch gravity sewer along E Lakewood Blvd towards 120th Ave.
Upcoming Work:
The closure of the Lakewood Blvd and 120th Ave intersection is scheduled for TUESDAY, JULY 28. See the map above for the detour routes. Local traffic will have access to their property for the duration of the closure.
Local traffic will have access as follows:
- 120th from Lakewood to James will have access from the north via James St.
- 120th from I-196 to Lakewood will have access from the south via I-196.
- Lakewood from US-31 to 120th will have access from the west via US-31.
- Lakewood from 112th to 120th will have access from the east via 112th.