Work Completed this past week (March 17-21)
- Horizontal Directional Drilling (water main) completed on Dewey and Red Bud.
- Main Street closed to through traffic from Front to Dewey Street.
- Removal of road and placement of gravel on Liberty Street complete. Opened to traffic on Wednesday (3/19)
- H pile install on 3rd Street complete
- Water main install on Dewey Street from Red Bud to Main Street complete.
- Reinstall of water main on 3rd Street complete (testing in progress).
- Fiberglass insert grouted for flume at WWTP.
- Installed first Sanitary manhole at WWTP (SNE3).
- Sanitary sewer bypass completed at WWTP, sewage from Ex. 15” sewer draining through new flume.
- K&R will not be working on Friday 3/21 (inhouse company-wide safety training).
Work planned for this week (March 24-28)
- Aerial steel work installing saddles on the creek cross will occur.
- 4 Insert-a-valves to be installed.
- Continue water main install on Main Street (Front to Dewey) and on Red Bud (North of 3rd Street).
- Water main shut down on 3rd Street (Red Bud to Skyline) for reconnection. Date of shut down unknown pending testing/sampling.
- Testing of water main in the area along 3rd street that was removed for excavation of the pH area material.
- 2 light poles on Red Bud will be removed.
- Continue sanitary sewer install from the WWTP.