Van Buren Street from Butternut to 136th Avenue is closed.
**The intersection of 152nd and Van Buren is closed for pipe installation.**
The intersection of 152nd and Van Buren is scheduled to be paved and opened to traffic by Friday, May 22.
The intersection of 160th and Van Buren is scheduled to close Tuesday, May 26. This closure is anticipated to last approximately two weeks.
The first layer of asphalt has been placed on most of the road between Butternut and 160th There are some gaps in the pavement to maintain access to the buried pipeline for internal work. Restoration along this corridor continues to progress.
Pipe laying has progressed through the intersection of 152nd.
Deep dewatering wells were installed at the intersection of 160th to help temporarily lower the groundwater table.
K&R mobilized their second pipe crew to east of 144th and will begin pipe installation this week if groundwater conditions permit.
Van Buren Street from US-31 to 120thAvenue is closed.
Pipe laying has progressed to approximately 600′ west of 120th The pipe has been plugged and the pipe crew has moved west to 144th.
Work on various pipe appurtenances and work inside the pipe will continue sporadically over the next several weeks.
Road restoration east of US-31 is scheduled to begin next week.
New Holland Street from 104thAvenue to 96th Avenue is closed.
The 54″ transmission main has been returned to service.
The 42″ transmission main was removed from service and the tie-in completed. Flushing and testing of the transmission main will begin tomorrow and the main will be returned to service soon.