WEDNESDAY, NOVEMBER 26, 2025

  • Van Buren Street from Butternut to 160th Avenue is closed. 160th to 152nd Avenue is scheduled to close next week.
  • K&R continued pipe laying in Van Buren Street and is progressing west to east. Pipe laying will continue next week. Approximately 1,800′ of pipe has been installed within this stretch.
  • Van Buren Street from US-31 to 128th Avenue is closed.
  • K&R continued pipe laying this week, progressing west to east. Pipe laying will continue next week. Approximately 300′ of pipe has been installed within this stretch.
  • Van Buren Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man installed the first valve vault of the project. Vault installation will continue next week.
  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Pipe deliveries finished on New Holland Street.
  • Excavation for the surge tank building foundation will tentatively begin next week.
Contact a Location
Learn About Us
View Our Services
Facebook-f Linkedin Youtube Instagram

© 2026 Prein&Newhof, All Rights Reserved

  • Plan Room
  • Lab Results
  • Construction Updates
  • Survey Request