Van Buren Street from Butternut to 160th Avenue is closed. 160th to 152nd Avenue is scheduled to close next week.
K&R continued pipe laying in Van Buren Street and is progressing west to east. Pipe laying will continue next week. Approximately 1,800′ of pipe has been installed within this stretch.
Van Buren Street from US-31 to 128th Avenue is closed.
K&R continued pipe laying this week, progressing west to east. Pipe laying will continue next week. Approximately 300′ of pipe has been installed within this stretch.
Van Buren Street from 104th Avenue to 96th Avenue is closed.
Ric-Man installed the first valve vault of the project. Vault installation will continue next week.
New Holland Street from 104th Avenue to 96th Avenue is closed.
Pipe deliveries finished on New Holland Street.
Excavation for the surge tank building foundation will tentatively begin next week.