Work completed/in progress:
- Sidewalk, stairs and transformer pad poured.
- Monorail hoist installed.
- Electrical equipment, wiring, and lighting installed.
- Began installation of suction piping, valves, and force mains
- Cleaned up and graded existing retention pond area.
Anticipated work activities for the coming week:
- Gravity sewer testing.
- Force main installation and testing.
- Generator and transformer installation.
- Continued mechanical and electrical equipment and wiring installation.