K&R has maintained two crews for work along 120th Ave and Lakewood Blvd. Along 120th a pipe crew continues to install 21-inch gravity sewer heading north towards James St. Along Lakewood Blvd, paving of the base and level course were completed last week. Driveway and top course paving are anticipated to be completed this week weather depending.