Frequently Asked Questions

Northland Drive Pedestrian Crossing at Rogue River Road

A pedestrian tunnel is being built under Northland Drive, along with approximately ½ mile of new paved trail on the east side of Northland Drive between 7 Mile Road and Cannonsburg Road.

The pedestrian tunnel will take pedestrians and cyclists safely underneath busy Northland Drive, connecting the recently completed South Rogue River Trail to upcoming trail extensions along Cannonsburg Road and Pettis Avenue, continuing toward Knapp Street in Ada Township.

Together, these projects will create a longer, more connected non-motorized route as part of the Grand River Greenway – a growing network of parks, trails, and natural areas linking West Michigan communities to the Grand River, from Lowell to the Lakeshore.

The pedestrian tunnel under Northland Drive will be 166 feet long and 18 feet wide with a 10 foot ceiling.

A tunnel provides a better experience for people using the trail. A bridge would require users to climb substantial ramps to get over Northland Drive, creating a longer and more difficult route. So, ultimately, the project team determined that going underneath the road provides a more direct and accessible connection for people of all ages and abilities.

Yes. To install the main tunnel sections, crews will temporarily close Northland Drive to all traffic after rush hour on Friday, Sept. 25 and open back up to traffic ahead of the morning commute on Monday, Oct. 5.

The closure will extend from Cannonsburg Road/West River Drive to Belding Road. However, the intersection of Rogue River Road/7 Mile Road and Northland Drive will be open to east-west traffic only.

A signed detour will route traffic via Belding Road, Myers Lake Avenue, and Cannonsburg Road.

Three security cameras will be installed inside the tunnel, and the approaches and inside of the tunnel and will be well lit.

During the weeklong closure of Northland Drive, crews will work around the clock to excavate a roughly 60-foot-wide trench across the roadway in order to place 19 concrete arch sections. Crews will also install storm piping and electrical conduit, then repave and restore the roadway above the completed structure.

The project is funded through a $10 million Michigan Department of Natural Resources grant to Downtown Grand Rapids, Inc.

The project also reflects years of partnership among Kent County, Plainfield Charter Township, the Michigan Department of Transportation, the Kent County Road Commission, Downtown Grand Rapids Inc., the Michigan Department of Natural Resources and other community partners.

The tunnel is being constructed as a permanent piece of the regional trail system, including infrastructure to manage water. Storm water will be collected in a new gravity storm system comprised of catch basins, trench drains and storm pipe.

The Northland Drive pedestrian tunnel is part of a larger regional trail system that is already seeing growing use. The project connects to the newly constructed South Rogue River Trail and advances the Grand River Greenway.

Together, these projects are working toward a continuous connection between Millennium Park and Lowell, providing more opportunities for people to walk, bike, and access the Grand River and surrounding natural areas.

For the latest construction updates, closure information, and project details, please visit the Prein & Newhof project page. You can also stay connected to this project and more by following Kent County Parks on Facebook and Instagram.

While crews finished installing the tunnel pieces under Northland Drive and reopened the road on Wednesday, Sept. 30, there’s still more work ahead before people can use it. Crews need to build the tunnel approaches, pave the trails, complete landscaping, and install lighting. The project is anticipated to be completed in spring 2027.