Site rebuilding continued last week with the placement of driveways, sidewalk, and asphalt base. Restoration will continue this week in preparation for the top course of asphalt.
Work Completed Last Week:
- Removed asphalt at the Terrace intersection.
- Aggregate base grading completed from Terrace to Wood.
- Asphalt base placed from Arthur to Wood.
- Continued placing driveway approaches and sidewalks from Terrace to Wood.
- Restoration of grass Continued on Catherine from Ransom to Wood.
Anticipated Work This Week:
- Raise manhole castings and valve boxes in preparation for top course of asphalt, tentatively scheduled for July 13th.
- Complete placing of sidewalk east of Terrace.
- Continue restoration of grass on Catherine east of Terrace.



