Plainfield Charter Township - Hills & Dales Water Main Replacement Phase 4

Important Information

Plainfield Charter Township is moving forward with plans to replace the aging cast iron water main in portions of the Hills & Dales neighborhood with new ductile iron water main. This project is part of the Township’s ongoing effort to improve water system reliability and enhance fire flow capacity within some of the Township’s original neighborhoods.

The Township has awarded the construction contract to Kentwood Excavating. Work is expected to take place between June and October 2026.

Existing water mains and water service lines will be completely replaced inside of the public road right-of-way. Portions of the road and storm sewer system impacted by water main construction will be replaced as necessary. Lawns and driveways disturbed by construction will be replaced as part of the project.

Access/Traffic:

Local traffic will be maintained during water main construction. There may be times when your driveway is inaccessible because water main construction is occurring in front of your house or driveway restoration is taking place. The contractor will work with you ahead of time and will make special access arrangements with you if needed.

Mail:

Mailboxes that interfere with water main construction will be temporarily relocated so that mail service can be maintained during construction. If your mailbox needs to be temporarily relocated, the contactor will inform you of where it has been moved to and when they anticipate it will be returned to its original location.

Garbage Pickup:

The contractor will work with you and your waste hauler to maintain service throughout construction. If water main construction interferes with your waste haulers ability to pick up your garbage, the contractor will temporarily move your garbage bins to a central location and return them to the end of your driveway by the end of the work day.

Water Service:

There will be times when your water service will be temporarily interrupted to facilitate water main connections or water service line replacement. The contractor or the Plainfield Water Department will inform you prior to this interruption taking place so that you can plan accordingly.

P&N Engineer:
Jeremy Kamp, PE
Senior Engineer
(616) 364-8491

P&N Construction Observer: Prein&Newhof will have a representative on site during construction.

Contractor:
Kentwood Excavating
Jonathan Roodvoets
(616) 949-5250

Plainfield Charter Township
Water Department
(616) 363-9660

powered by Advanced iFrame

You have likely seen various activities on site over the last week. Miss Dig flags have been placed and are marking existing underground utilities, construction staking is underway, and driveway/road removals have been marked out.

Kentwood Excavating plans to have a crew on site starting next week to begin water main construction along Hillsdale Avenue. Construction will begin at the Hillsdale and Eldon intersection and progress south.

Progress Report:

This week trees and bushes were marked for removal with orange paint. Tree clearing will begin the week of June 15. Water main construction may begin as early as the week of June 22.

Progress Report:

Tree clearing and water main construction are planned to begin in the second half of July. Construction will remove landscaping within the road right-of-way and it will not be replaced as part of this project. If you have landscaping within 20 feet of the edge of the road and would like it save it, we recommend that it be moved prior to construction starting.