Important Information

Contract 3: Construct force main from Heights Ravenna Road to Muskegon County Resource Recovery Center.

Access/Traffic: Local traffic will be maintained during pipeline construction. There may be times when your driveway is inaccessible because pipeline construction is occurring in front of your house or driveway restoration is taking place. The contractor will work with you ahead of time and will make special access arrangements with you if needed.

Mail: Mailboxes that interfere with pipeline construction will be temporarily relocated so that mail service can be maintained during construction. If your mailbox needs to be temporarily relocated, the contractor will inform you of where it has been moved to and when they anticipate it will be returned to its original location.

Garbage Pickup: The contractor will work with you and your waste hauler to maintain service throughout construction. If pipeline construction interferes with your waste haulers ability to pick up your garbage, the contractor will temporarily move your garbage bins to a central location and return them to the end of your driveway by the end of the work day.

Contact

Prein&Newhof – Field
Dave Cadena
(231) 670-7017
dcadena@preinnewhof.com

Contractor
Kamminga & Roodvoets
(616) 949-0800

Muskegon County
(231) 724-3440

powered by Advanced iFrame



  • The force main is active and MCRRC is receiving flow from the Coopersville area.
  • Restoration and punch list work continues.
  • Moorland Road bridge work at Crockery Creek will be completed next week. After completion of the bridge, all major work scope items on the force main project will have been completed.
  • Pipeline construction complete. Restoration and punch list work continues.
  • Crews will be working on force main structures this week.

Work completed/in progress:

  • Pavement markings on Sherman and Price have been completed.
  • Field drives placed along Price Road.
  • Continued installation of the HDPE discharge outlet piping at the lagoon.

Anticipated work activities for the coming week:

  • Forming and pouring 36″ concrete blowoff structure and splash pad at the lagoon.
  • Continue restoration and punchlist efforts

Work completed/in progress:

  • Completed paving HMA base course on Price Road.
  • HMA top course on Price Road being placed today.

Anticipated work activities for the coming week:

  • Install Pavement markings on Sherman Blvd today
  • Continue HDPE force main installation of the discharge outlet piping at the lagoon.
  • Continue restoration and punchlist efforts

**Sherman Boulevard is closed from Ensley Road to Price Road.**

**Price Road is closed from Sherman Boulevard to Moorland Road.**

 

Work completed/in progress:

  • Paved top course on Sherman Blvd.
  • Completed force main installation on Price Road.
  • Contract 2/Contract 3 connection made.
  • Hydrostatic test performed and completed.

Anticipated work activities for the coming week:

  • Continue restoration and punchlist efforts
  • Prepare for Price Road paving.
  • Continue force main installation at Hall Road including outlet lagoon discharge piping.

 

**Sherman Boulevard is closed from Ensley Road to Price Road.**

**Price Road is closed from Sherman Boulevard to Moorland Road.**

 

Work completed/in progress:

  • Performed hot tap of 60″ force main near MCRRC.
  • Force Main installation along Price Rd is completed.
  • Concrete restraint collars for force main are completed.
  • Driveway culverts and cross culverts along Price Rd have been installed.
  • Paved HMA base course on Sherman Blvd.
  • Paved HMA base course on Price Rd.

Anticipated work activities for the coming week:

  • Continue force main installation near Hall Rd on MCRRC property and on the corner of Price Rd and Heights Ravenna Rd.
  • Grade ditches along Price Rd.
  • Pave remainder of HMA base course on Price Rd.
  • Pave HMA wedging on Sherman Blvd.
  • HMA top course on Price Rd and Sherman Blvd is tentatively scheduled for the week of Nov. 10

 

**Sherman Boulevard is closed from Ensley Road to Price Road.**

**Price Road is closed from Sherman Boulevard to Moorland Road.**

Work completed/in progress:

  • Continued installing force main pipe along Price Rd.
  • Continued grading sand subbase and aggregate base on Price Rd.
  • Placed HMA base course on Sherman Blvd.
  • Placed curb & gutter at Price & Sherman and at Sullivan & Apple.
  • Abandoned dewatering sock pipe and kelly wells along Apple Ave.

Anticipated work activities for the coming week:

  • Pave HMA top course on Sherman Blvd.
  • Continue grading sand subbase and aggregate base on Price Rd.
  • Replacement of driveway and cross culverts on Price Rd.
  • 60″ hot tap and valve placement near Hall Rd on MCRRC property.

**Sherman Boulevard is closed from Ensley Road to Price Road.**

**Price Road is closed from Sherman Boulevard to Moorland Road.**

** Sullivan Road is closed at Apple Avenue.**

Work completed/in progress:

  • Sherman Blvd has been pulverized, and ditches have been graded.
  • Completed cross culverts under Sherman Road.
  • Continued force main installation along Price Road.
  • Installed multiple concrete restraint collars.

Anticipated work activities for the coming week:

  • Continue force main installation along Price Road.
  • Grade ditches along Price Road.
  • Pave base course of HMA on Sherman Blvd. Paving is scheduled for Wednesday (10/15).
  • Pave top course of HMA on Sherman Blvd. Paving is scheduled for Friday (10/17).

**Sherman Boulevard is closed from Ensley Road to Price Road.**

**Price Road is closed from Sherman Boulevard to Moorland Road.**

** Sullivan Road is closed at Apple Avenue.**

Work completed/in progress:

  • Force main installation along Price Rd continues.
  • Force main tie-in north of Apple Avenue underway.
  • Road building underway on Sherman Blvd and Price Rd.
  • Most culvert crossings completed.

Anticipated work activities for the coming week:

  • Continue force main installation along Price Rd.
  • Pulverize remainder of Sherman Blvd and continue road building.