West Randall Lift Station

Important Information

West Randall Lift Station: Construct a second lift station adjacent to the existing West Randall Lift Station to accommodate proposed flows for the Southeast Regional Force Main.

Contact

Prein&Newhof
Will Thies, PE
(616) 364-8491
wthies@preinnewhof.com

Contractor
Grand River Construction
(616) 669-5611

Muskegon County
(231) 724-3440

Work completed/in progress:

  • Meter chamber set.
  • Ductile Iron gravity sewer and force main pipe delivered to site.
  • Existing storm sewer removed
  • Unit heaters installed.

Anticipated work activities for the coming week:

  • Install 48″ gravity sewer into wet well.
  • Partial installation of storm sewer.
  • Regrading of north side of site in preparation for force main installation.

Work completed/in progress:

  • Exterior equipment pads poured.
  • Ductwork, louvres, monorail, and doors installed.
  • Wet well coating completed and tested.

Anticipated work activities for the coming week:

  • Electrical and mechanical work will continue.

Work completed/in progress:

  • Wet well coating began.
  • Metal roof completed.

Anticipated work activities for the coming week:

  • Continue wet well coating.
  • Install soffit, fascia, and vents.
  • Pour equipment pads.
  • Continue conduit and ductwork installation.

Work completed/in progress:

  • Metal roof installation continues.
  • Preparation for wet well lining complete.
  • Interior walls painted.

Anticipated work activities for the coming week:

  • Begin wet well coating.
  • Complete metal roof installation.
  • Pour equipment pads.

Work completed/in progress:

  • Dry well stair installation nearly completed.
  • Metal roof installation started.
  • Continue preparation for wet well lining.

Anticipated work activities for the coming week:

  • Continue roof construction and preparation for wet well lining.
  • Begin painting interior walls

Work completed/in progress:

  • Continued preparation for wet well lining, and dry well stair installation.
  • Block filler applied.

Anticipated work activities for the coming week:

  • Continue roof construction, preparation for wet well lining, and dry well stairs installation.
  • Install dry well ductwork and conduit.
  • Begin painting interior walls

Work completed/in progress:

  • Roof construction in progress
  • Preparation for wet well lining
  • Began dry well stairs

Anticipated work activities for the coming week:

  • Continue roof construction, preparation for wet well lining, and dry well stairs
  • Install dry well ductwork
  • Begin painting interior walls

Work completed/in progress:

  • Precast concrete plank ceiling was installed.
  • Roof trusses were placed.
  • Steel stair installation began.

Anticipated work activities for the coming week:

  • Steel stair installation will be completed.
  • Pump suction pipe installation will begin.

Work completed/in progress:

  • Masonry and conduit installation continued.
  • Drain and water lines were installed in the dry well.
  • Masonry work was completed.

Anticipated work activities for the coming week:

  • Precast concrete plank ceiling will be placed.

Work completed/in progress:

  • Masonry installation progressed. The interior walls and the north exterior wall are now complete.
  • Pump pads and wet well hatch curbs were poured.

Anticipated work activities for the coming week:

  • Masonry and drain pipe installation will continue.