Work completed/in progress:
- Meter chamber set.
- Ductile Iron gravity sewer and force main pipe delivered to site.
- Existing storm sewer removed
- Unit heaters installed.
Anticipated work activities for the coming week:
- Install 48″ gravity sewer into wet well.
- Partial installation of storm sewer.
- Regrading of north side of site in preparation for force main installation.