Plainfield Charter Township - Northgate Phase 1 and 2 Water Main Replacement

Project Information

Access/Traffic: Local traffic will be maintained during water main construction. There may be times when your driveway is inaccessible because water main construction is occurring in front of your house or driveway restoration is taking place. The contractor will work with you ahead of time and will make special access arrangements with you if needed.

Mail: Mailboxes that interfere with water main construction will be temporarily relocated so that mail service can be maintained during construction. If your mailbox needs to be temporarily relocated, the contactor will inform you of where it has been moved to and when they anticipate it will be returned to its original location.

Garbage Pickup: The contractor will work with you and your waste hauler to maintain service throughout construction. If water main construction interferes with your waste haulers ability to pick up your garbage, the contractor will temporarily move your garbage bins to a central location and return them to the end of your driveway by the end of the work day.

Water Service: There will be times when your water service will be temporarily interrupted to facilitate water main connections or water service line replacement. The contractor or the Plainfield Water Department will inform you prior to this interruption taking place so that you can plan accordingly.

Contact

P&N Engineer
Jeremy Kamp, PE
Project Engineer
(616) 432-6709
jkamp@preinnewhof.com

P&N Construction Observer
Prein&Newhof will have staff on-site throughout construction.

Contractor (Phase 1)
Milbocker & Sons, Inc.
(269) 673-2195

Contractor (Phase 2)
Montgomery Excavating
(616) 502-7799

Plainfield Township
Water Department
(616) 363-9660

The final concrete work was completed this week. Montgomery will be back in the next few weeks to finish up lawn restoration around these areas. Montgomery is also coordinating with the paving contractor to complete the last little bit of road patching.

We are aware of some areas where the original seeding did not take very well, and we are working with Montgomery on addressing these areas. We ask that residents continue to water the newly planted lawns. Montgomery has been periodically watering the new grass to help promote good growth at the start. However, it is each individual residents responsibility to water, fertilize, and cut the new grass just as you would the rest of your yard. It will likely take a year or two for the new grass to fill out and match your existing grass and the look may vary depending on how it is cared for.

Montgomery has scheduled street sweepers for 8:00 am Friday (5/23) morning on Audley, Daylor, and Northgate. Please move vehicles off the road so that the streets can be cleaned.

 

Over the next few weeks, Montgomery will complete lawn restoration, punch list items, and final project clean up. There is some remaining concrete work that will be completed at the end of the project once Montgomery has their staging area in the park on Northgate cleaned up.

We want to remind residents to water the new grass seed once Montgomery has completed the hydroseed process. Daily watering for the first two weeks is recommended to keep the seeds moist which will help the seed germinate. Regular watering throughout the summer will ensure that a good stand of grass is produced by this fall. Residents are responsible for watering their lawns after Montgomery completes the restoration work.

This Week:

Montgomery prepared driveway ends for paving where necessary. Great Lakes Paving will be on site today (Friday) to complete the patch repairs. Montgomery also worked on spreading topsoil in preparation for seeding.

Next Week:

Montgomery will continue lawn restoration work and project cleanup. Any paving work that is not completed today will be finished up next week. There is a little outstanding concrete work that will take place once Montgomery has most of the project cleanup completed.

Residents are asked to not park on newly seeded lawn areas. Montgomery will not reseed areas that are continuously parked on. It is also the residents responsibility to water the newly seeded lawn areas to promote good grass growth.

This Week: The majority of the week was spent replacing concrete sidewalk and driveways on Daylor and Northgate. Montgomery continued to clean up the project site and began preparing for road and lawn restoration .

Next Week: Montgomery will continue lawn restoration work next week. Some of the existing concrete driveways were under the edge of the existing road. This will require that Montgomery patches the asphalt road at the end of these driveways. Montgomery will begin preparing these driveways for paving middle of next week.

This Week:

The final water main tie-in was completed along Northgate on Monday. Montgomery spent the rest of the week prepping for sidewalk and driveway construction which is scheduled for next week. The old water main was abandoned by pumping flowable fill (light weight concrete) into the old pipe.

Next Week:

Concrete crews will be on site to replace sidewalk and driveways. Montgomery will work on lawn restoration and project cleanup.

This Week:

  • Montgomery completed water service installation on Northgate.
  • Montgomery completed water main tie-ins at Daylor and the north end of Northgate.
Next Week:
  • Montgomery will complete the last water main tie-in at the south end of Northgate. This is tentatively scheduled for Monday.
  • Montgomery will begin project cleanup.
  • Concrete sidewalk will begin to be replaced.

This Week:

  • Montgomery completed testing on Northgate (south of Eldon). Disinfection test results will be in on Saturday.
  • Montgomery installed water services on Daylor and Northgate (north of Eldon).
Next Week:
  • Montgomery will finish installing water services on Northgate (north of Eldon).
  • Montgomery will install water services on Northgate (south of Eldon) pending passing disinfection test results.
  • Sidewalks on Daylor and Northgate (north of Eldon) will be staked, and Montgomery will start grading in preparation for concrete crews to arrive on site within the next week.

This Week:

  • Montgomery completed water main installation on Northgate (south of Eldon).
  • Montgomery worked with the Plainfield Water Department to disinfect the new water mains on the south half of Daylor and Northgate (north of Eldon)

Next Week:

  • Montgomery will work with the Plainfield Water Department to pressure test and disinfect the new water main on Northgate (south of Eldon).
  • Montgomery will begin installing water services on Daylor and then move to Northgate (north of Eldon).
  • Double KK Underground will be on site Monday or Tuesday to directionally-drill new water services under the road for Montgomery.

This Week:

  • Montgomery installed the new water main on Northgate (north of Eldon).
  • Montgomery stripped topsoil and removed sidewalk along Northgate (south of Eldon).
  • Montgomery filled and flushed the new water mains on Northgate and Daylor. Pressure testing of these new water mains is taking place today.

Next Week:

  • The existing water main on Northgate (south of Eldon) will be shut down Monday morning to connect the new water main to the existing water main valve from phase 1 at Miramar. Residents whose water service will be temporarily impacted should have already received a shut off notice door hanger.
  • Montgomery will also be digging up the existing hydrants they need to pass by with the new water main during this shutdown to verify current conditions.
  • Montgomery will begin installing water main along Northgate starting at Miramar and working north.
  • Montgomery will work with the Township Water Department to complete disinfection testing of the new water mains on Daylor and Northgate (north of Eldon). Do not be alarmed if you see large amounts of water coming out of hydrants – this is intentional.