City of Coopersville - River Street Reconstruction

Important Information

The City of Coopersville will be reconstructing River Street from Randall Street to the dead end cul de sac including all concrete curb and gutter and driveway approaches. Sanitary sewer and storm sewer utilities will also be reconstructed between O’Malley Drive and Randall Street as part of this project. River Street will be closed to through traffic, but will remain open to residents. Businesses located south of the project will be asked to utilize O’Malley Drive for access.

K&R will start construction with tree clearing and road removals the week of March 18, 2024, and continue with sanitary sewer construction. The project is anticipated to be completed by the middle of July, 2024.

During sanitary sewer construction, River Street will be blocked off for through access at the location of the sanitary sewer excavation. As sewer construction continues north, the direction of access to each property will be affected and will change with the progress of construction. Vehicles will have to access their property from either O’Malley or Randall Ave.

Access/Traffic

  • Emergency Vehicle Access to be Maintained.
  • Temporary access to be maintained to residents
  • There will be times where access will be limited to your home during paving and concrete construction – Contractor to coordinate alternate parking location
  • Businesses on the south of River Street are asked to use O’Malley Drive for access

Mail
Temporary mailbox location may be installed at Court Street and Metal Works Drive. Contractor to coordinate.

Garbage Pickup
Contractor may request trash receptacles to be placed at the road the night before.

Water Service
The City will be replacing any galvanized steel, lead, or plastic water services found during water main construction. If found, Water Services will be replaced from the new main to the curb stop box at the right of way line. There will be a 2–3-hour window of water shutoff for these connections. A few residents with galvanized services will have services replaced into their home and will be coordinated with Contractor/Plumber.

P&N Engineer
Richard Taglione, PE, Project Engineer
906-369-0239
rtaglione@preinnewhof.com

P&N Construction Observer
Jedadiah Lee, Construction Observer
231-288-7775
jlee@preinnewhof.com

Contractor
Melanie Hoffman, Project Manager
Kamminga & Roodvoets, Inc. (K&R)
616-949-0800
hoffmme@kandrinc.com

Client
Bryan Buist, Department of Public Works Supervisor
616-997-9731
bbuist@cityofcoopersville.com

Progress Report: K&R made approximately 300′ of progress with sanitary sewer construction to the north. Pipe Installation is approximately to 400′ south of Court St.

Upcoming Work: K&R will continue sanitary sewer construction progressing to the north. K&R may also start storm sewer construction on River Street in the area where sanitary sewer construction has been completed.

Extra Notes:

During sanitary sewer construction, River Street will be blocked off for through access at the location of the sanitary sewer excavation. As sewer construction continues north, the direction of access to each property will be affected and will change with the progress of construction. Vehicles will have to access their property from either O’Malley or Randall Ave.

Driveway access to River Village and The Meadows is expected to be impacted next week. K&R has constructed a temporary gravel driveway between the parking lots of the two communities. Access to the complexes will be maintained utilizing either entrance, depending on which one is affected by sanitary sewer installation.

Progress Report: K&R made progress with sanitary sewer construction to the north to approximately 300 feet north of the River Street/Skeels Street intersection.

Upcoming Work: K&R will continue sanitary sewer construction progressing to the north. K&R will also start storm sewer construction on River Street in the area where sanitary sewer construction has been completed.

Extra Notes: K&R will notify residents as driveway access becomes limited due to pipe installation. Residents are reminded to stay clear of construction equipment and excavations on the project site.

During sanitary sewer construction, River Street will be blocked off for through access at the location of the sanitary sewer excavation. As sewer construction continues north, the direction of access to each property will be affected and will change with the progress of construction. Vehicles will have to access their property from either O’Malley or Randall Ave.

Progress Report: K&R made progress with sanitary sewer construction to the north approximately 90 feet including the connection to the existing sewer at the River Street/Skeels Street intersection.

Upcoming Work: K&R will continue sanitary sewer construction progressing to the north.

 

Extra Notes:

K&R will notify residents as driveway access becomes limited due to pipe installation. Residents are reminded to stay clear of construction equipment and excavations on the project site.

During sanitary sewer construction, River Street will be blocked off for through access at the location of the sanitary sewer excavation. As sewer construction continues north, the direction of access to each property will be affected and will change with the progress of construction. Vehicles will have to access their property from either O’Malley or Randall Ave.

Progress Report: K&R continued mobilizing equipment and materials to the project location. Dewatering equipment was set up at the intersection of River Street and Skeels Street to accommodate groundwater conflicts for sanitary sewer constriction.

Upcoming Work: K&R will continue sewer construction starting at the Skeels Street intersection progressing to the north.

Extra Notes: K&R will notify residents as driveway access becomes limited due to pipe installation. Residents are reminded to stay clear of construction equipment and excavations on the project site.

 

Progress Report:

K&R pulverized the asphalt on River Street and Court Street, leaving the material in place. Tree removal as well as curb and gutter removal south of O’Malley Drive also occurred last week. Construction equipment was mobilized at the River Street Cul-De-Sac and existing underground utilities have been exposed utilizing a vac truck. Mailboxes have been moved to centralized locations near the Court Street and O’Malley Drive.

Upcoming Work:

K&R will begin sanitary sewer installation next week on Monday, March 25. Sanitary sewer construction will begin near the Skeels Street intersection and will progress north. K&R will notify residents as driveway access becomes limited due to pipe installation.

Extra Notes:

Residents are reminded to stay clear of construction equipment and excavations on the project site.

Progress Report:  K&R has started staging equipment on the project site, and construction signage has been installed. MISS DIG has located underground utilities on the project limits with multi colored paint and flags.

Upcoming Work:  Construction activity on River Street will begin on March 18, 2024. The Contractor will start road removals and tree removals on Monday, March 18, and will continue with locating existing utilities with a vac truck. Access will be maintained throughout the project site with gravel materials. Please use caution when driving or walking around construction equipment.