The focus this week was on completing the Phase 1 storm sewer and placing aggregate base in preparation for installing curb. The focus next week will be on installing the curb, sidewalks, and driveway approaches.

 

Work Completed This Week

  • Contractor shaped the road and placed aggregate grade in preparation to place curb & gutter.
  • Contractor abandoned old sanitary sewer and old watermain.
  • Contractor completed all storm sewer on Phase 1.
  • Contractor began grading of sidewalk and drive approaches.

 

Anticipated Work Next Week

  • Placing sidewalk and drive approaches.
  • Placing curb & gutter

 

Please note that Phase 2 of the project is scheduled to begin on June 9th.  The completion date of Phase 1 is tentatively scheduled for June 23rd.