Progress Report:
48th Avenue: The contractor completed the section of water main in the project limits of the roundabout at the intersection and connected their water main to the existing water main on Baldwin Street. The contractor also continued to restore the roadway in 48th Avenue to prepare for paving.
Tyler Street: The contractor finalized restoration on the site and planted grass seed in the areas disturbed by the project.
Upcoming Work:
48th Avenue: The contractor will begin testing of the water main they installed in the intersection next week. The contractor hopes to pave 48th Avenue south of Oak Lane Drive around the end of August and finish installing the water main once they receive all of their materials around the middle of September. Following that they will finish the road restoration. The contractor for the roundabout will begin construction for the roundabout when the water main has passed testing in the intersection. It is anticipated that roads will be fully reopened by the end of October.
Notes:
48th Avenue remains closed to through traffic from Port Sheldon Street to Baldwin Street. The intersection at Baldwin Street and 48th Avenue remains closed from every direction for the roundabout construction. Through traffic should continue to follow the posted detour signage.
Residents along 48th Avenue should be aware that crews will be on site restoring the roads and greenspace around the roads.
Local traffic needing access to Sutherland Springs Condominium should do so by turning onto 48th Avenue from Port Sheldon Street if possible. While the contractor will continue to maintain access to 48th Avenue from either direction, dump trucks will be lined up north of Tyler Oaks Drive later in the week.
We ask the public to respect the workers and the closed road. Police will continue to monitor the site to ensure safe working conditions and to ensure the road is only being used by those who live or work on this road. Local traffic should continue to be especially mindful as there will be multiple crews on site next week. The contractor is aware of the difficult traffic situation and will accommodate to the best of their ability.







