Here is another weekly update on the recent work performed in Muskegon Heights on water main and road improvements.
Progress Report
- Broadway: All water main is now installed. The last section between Temple and 9th Street is undergoing testing before it can be connected to the existing system next week.
- Broadway: Sanitary sewer manholes are being replaced in intersections
- Broadway: Crews were preparing to install underdrain and prepare the road for gravel road base between 5th and 7th Streets
- The temporary cell tower near the Getty Tank is up and running and the equipment is off of the Tank. The tank repainting will begin soon.
- Delano Avenue: Water main connections were made in several locations along Delano
The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.
The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street
Upcoming Work Planned for Next Few Weeks:
- Broadway: Sanitary sewer manholes will be replaced in the intersections of 9th and 8th Streets and the sewer main will be replaced between Temple and Waalkes
- Broadway: Water main will be connected to the new system and the last few water services will be replaced between Temple and 9th Streets
- Broadway: Storm drain work will take place between 9th and 5th Streets
- Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
- Additional water main connections will take place down Delano east of Wood Street
- Storm drains will be replaced in the intersections of Delano and Howden and Wood
- Water main replacement and road improvements will begin soon on Sanford Street between Oakwood and Norton, and on Maplewood between Sanford and Jefferson