Progress Report
- Broadway: The road was opened last Friday to traffic. Only punch list items remain.
- Delano Avenue: The final course of asphalt was installed today. The road is now open to all traffic.
- Sanford Street: Concrete work was completed, the first course of asphalt was installed and manhole and valve structures are being raised to the final elevations. The road is still closed to thru traffic.
- Oakwood Avenue: Underground utility work was completed this week with the final water main tie-ins and storm drain work in the Waalkes and Lemuel intersections
- Amsterdam Avenue: All water main work is complete and tied in to the distribution system.
- Getty Tank: Priming and painting of the tank continues. Roughly 60% of the work is complete now. Additional coats of paint will be done on the exterior.
- Approximately 75 lead water service lines were removed this week
The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue.
Upcoming Work Planned for Next Few Weeks:
- Water service replacements are happening all over the City as part of the Lead Service Line Replacement program.
- Delano: Final restoration and new signs will be installed
- Sanford: Finish raising structures, final restoration, new signs, and the final course of asphalt is tentatively scheduled for Wednesday, August 19. The road should be open to traffic by the end of the week.
- Oakwood: Concrete curb and gutter, road gravel, and road restoration
- Amsterdam: Sanitary sewer manholes will be replaced in the intersections of Glendale, Jefferson, and 5th Street. New storm drains will be installed.
- Getty Tank: Additional coats of paint will be done, interior work will be done, and new fencing and gates will be installed