City of Muskegon Heights - 2026 Road & Water Main Construction

Important Information

The work will involve replacement of water mains, valves, hydrants, and water services in the street, including new road where the water main is reconstructed. New ramps and sidewalks will also be constructed where they are disturbed for the work.

Garbage Service:
Customers are encouraged to add a piece of tape to their cart and to clearly write their address on their cart. Service will remain and the Contractor will assist with getting your cart picked up and returned on your regular garbage days if the road in front of your home or business is inaccessible to garbage trucks.

Mail Service:
Post deliveries will be maintained throughout the project.

Access/Traffic:
Work will result in full closure within the construction areas as noted on the map shown. Follow the updates for specific closure dates. Broadway Avenue detour will be Glade to Summit to Peck Street.  Temple and 6th Streets will be open as much as possible to cross Broadway. Otherwise, all other side streets will be closed at Broadway. Thru traffic will be prohibited in all construction areas.

1. Broadway, Phase 3 – Glade to 5th Street

Project Timeframe: March 2, 2026 – Labor Day 2026
Contractor: McCormick Sand of Twin Lake, MI
24- hour Emergency Number: Rob Murphy, 231.740.8894
City Contacts:
John Allen, Utilities Director
231) 955-0050
Khi Guy, Public Works Director
(231) 332-6762
Primary Project Contact:
Metro Consulting Associates
Ashwini Tapase, (313) 410-9384
Prein&Newhof Contact:
Matt Hulst, (231) 799-9093

 

2. Delano, Reynolds to Getty

Project Timeframe:  Mid April 2026 – August 2026
Contractor: Terra Contractors of Muskegon, MI
24-hour Emergency Number:
Jason Franklin, (231) 206-7030
Primary Project Contact:
Dan Sorek, (616) 218-2940

 

3. Sanford, Phase 2 – Oakwood to Norton and Maplewood, Jefferson to Sanford

Project Timeframe: Late April, 2026 – August 2026
Contractor: Jackson-Merkey Contractors of Muskegon, MI
Primary Project Contact:
Dan Sorek, (616) 218-2940

 

4. Oakwood, Glade to Mona

Project Timeframe: Summer 2026 – Fall 2026
Contractor: McCormick Sand of Twin Lake, MI
24- hour Emergency Number:
Rob Murphy, (231) 740-8894
Primary Project Contact:
Dan Sorek, (616) 218-2940

 

5. Norton, Park to Peck

Project Timeframe: Summer 2026 – Fall 2026
Contractor: McCormick Sand of Twin Lake, MI
24- hour Emergency Number:
Rob Murphy, (231) 740-8894
Primary Project Contact:
Dan Sorek, (616) 218-2940

 

6. Amsterdam, 6th to Peck

Project Timeframe: Summer 2026 – Fall 2026
Contractor: McCormick Sand of Twin Lake, MI
24-hour Emergency Number:
Rob Murphy, (231) 740-8894
Primary Project Contact:
Dan Sorek, (616) 218-2940

 

7. Getty Water Tank Repainting

Project Timeframe: May 2026 – August 2026
Contractor: Seven Brothers Painting of Shelby Township, MI
Primary Project Contact:
Peter Brink, (231) 798-0101

 

8. Water Filtration Plant and Low Lift Pump Station Improvements

Project Timeframe: March 2026 – 2027
Contractor: Franklin Holwerda Company of Wyoming, MI
Primary Project Contact:
Peter Brink, (231) 798-0101

Projects

  1. Broadway, Phase 3 – Glade to 5th Street
  2. Delano, Reynolds to Getty
  3. Sanford, Phase 2 – Oakwood to Norton and Maplewood, Jefferson to Sanford
  4. Oakwood, Glade to Mona
  5. Norton, Park to Peck
  6. Amsterdam, 6th to Peck
  7. Getty Water Tank Repainting
  8. Water Filtration Plant and Low Lift Pump Station Improvements
    (2323 Seminole Rd, not mapped)

Progress Report

  • Broadway: The road was opened last Friday to traffic. Only punch list items remain.
  • Delano Avenue: The final course of asphalt was installed today. The road is now open to all traffic.
  • Sanford Street: Concrete work was completed, the first course of asphalt was installed and manhole and valve structures are being raised to the final elevations. The road is still closed to thru traffic.
  • Oakwood Avenue: Underground utility work was completed this week with the final water main tie-ins and storm drain work in the Waalkes and Lemuel intersections
  • Amsterdam Avenue: All water main work is complete and tied in to the distribution system.
  • Getty Tank: Priming and painting of the tank continues. Roughly 60% of the work is complete now. Additional coats of paint will be done on the exterior.
  • Approximately 75 lead water service lines were removed this week

The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue.

 

Upcoming Work Planned for Next Few Weeks:

  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program.
  • Delano: Final restoration and new signs will be installed
  • Sanford: Finish raising structures, final restoration, new signs, and the final course of asphalt is tentatively scheduled for Wednesday, August 19. The road should be open to traffic by the end of the week.
  • Oakwood: Concrete curb and gutter, road gravel, and road restoration
  • Amsterdam: Sanitary sewer manholes will be replaced in the intersections of Glendale, Jefferson, and 5th Street. New storm drains will be installed.
  • Getty Tank: Additional coats of paint will be done, interior work will be done, and new fencing and gates will be installed

 

Broadway, looking east from Temple

 

Broadway looking west from 6th Street

 

New asphalt at Ray and Delano

 

Paving operations on Sanford, north of Maplewood

Progress Report

  • Broadway: Restoration efforts are complete; the final course of asphalt was installed, and striping will be completed today. The road should be open to traffic by the end of the day today!
  • Delano Avenue: Underground utility work is complete. Road and lawn restoration is ongoing. The last concrete was poured this week.
  • Sanford Street: Concrete curb and gutter was installed, concrete sidewalk, driveways and ramps are planned to be poured today. Road gravel base was installed, spread and graded for asphalt next week.
  • Oakwood Avenue: Water main connections took place at Lemuel and work is being done in Waalkes with new storm drains and water main connections.
  • Amsterdam Avenue: New water main is now in service and customers are being connected to the new water main, and lead service lines are being replaced.
  • Getty Tank: Priming and painting of the tank continues. Roughly 50% of the work is complete now. Additional coats of paint will be done on the exterior.
  • Over 50 lead water service lines were removed this week

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue

 

Upcoming Work Planned for Next Few Weeks:

  • Broadway: Punchlist work, removal of traffic control signage, cleanup.
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program.
  • Delano: Final paving, restoration. The road should be open to traffic next week.
  • Sanford: Asphalt paving, structure adjustments and then the final course of asphalt late in the week. The road should be open to traffic by the end of the week.
  • Oakwood: Restoration of utilities in Lemuel and Waalkes and the road reconstruction with concrete curb and gutter, sidewalk ramps
  • Amsterdam: Water services will be replaced, additional water main connections, and the old water main will be taken out of service. The water main connections, when done, will connect water mains in 5th, Glendale, and Jefferson all in one day, and there will be temporary water disruptions for a large number of customers (roughly 100) between Norton and Summit, 6th Street to Sanford.
  • Getty Tank: Additional coats of paint will be done, interior work will be done, and new fencing and gates will be installed

Sorry, no pictures this week, but we’ll have some great shots of new asphalt and open roads next week!

Progress Report

  • Broadway: Restoration efforts are nearly complete. All structures were raised and the site is being cleaned and prepared for final paving next week. THE ROAD IS STILL CLOSED TO ALL TRAFFIC.
  • Delano Avenue: Underground utility work is complete. Road and lawn restoration is ongoing. The first course of asphalt was placed at all intersections except Riordan and Wood. Utility poles were replaced at these intersections this week.
  • Sanford Street: Concrete curb and gutter was installed, areas have been prepped for new sidewalks and driveway approaches
  • Oakwood Avenue: Water main connections are taking place along Oakwood between Glade and Mona. Many connections are complete.
  • Amsterdam Avenue: New water main was tested for connection to the system
  • Getty Tank: Priming and painting of the tank continues. Roughly 50% of the work is complete now. New concrete curb was poured at the entrance by the cemetery, and the first course of asphalt was installed
  • Over 60 lead water service lines were removed this week

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue

 

Upcoming Work Planned for Next Few Weeks:

  • Broadway: Final cleanup, paving and pavement markings will be completed and the road is planned to be open to traffic by this time next week.
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program.
  • Delano: The intersections of Wood and Riordan will be completed. Final paving should take place the week of August 10
  • Sanford: Concrete sidewalk, ramps and driveway approaches will be poured. The first course of asphalt will be installed. Manholes and valves will be adjusted to grade.
  • Oakwood: Water main connections will continue in Lemuel and Waalkes. After they are completed, road restoration will take place at all sites.
  • Amsterdam: Water services will be replaced
  • Getty Tank: Painting will continue, new fencing and gates will be installed
New concrete curb and gutter near the tank driveway in the cemetery

 

Paving taking place in the cemetery

 

New concrete curb and gutter on Sanford, looking north from Maplewood

 

 

Crews adjusting a hydrant on Delano

 

New asphalt in the intersection of Elwood and Delano

Progress Report

  • Broadway: Restoration work is ongoing with final touches to concrete and structure adjustments before the final course of asphalt is placed soon. THE ROAD IS STILL CLOSED TO ALL TRAFFIC.
  • Delano Avenue: Underground utility work is essentially complete, and road restoration is waiting for a couple of utility poles to be relocated next week. Road restoration should be complete in the next few weeks.
  • Sanford Street: Underground utilities are completed and the road is being rebuilt now. Gravel road base is being placed now.
  • Oakwood Avenue: Water main connections are taking place along Oakwood between Glade and Mona. Many connections are complete.
  • Amsterdam Avenue: Water main is installed and will be tested before connection to the City system next week.
  • Getty Tank: Sandblasting and painting of the tank continues. Roughly 40% of the work is complete now.
  • Lead Service Lines continue to be replaced throughout the City

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue

Upcoming Work Planned for Next Few Weeks:

  • Broadway: Manhole and valve structures will be raised in the new asphalt. Final restoration and paving will be done in the next 2 weeks.
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program. This work will dramatically increase next week through August.
  • Delano: Road and lawn restoration will take place between Reynolds and Getty after the paving is completed in the next 2 weeks.
  • Sanford: Gravel road base will continue to be placed and concrete curb and gutter will be installed next week along with new concrete sidewalk and driveway ramps.  Asphalt will be done the first week of August.
  • Oakwood: Water main connections will continue in Lemuel and Waalkes. After they are completed, road restoration will take place at all sites.
  • Amsterdam: Water main will be tested next week before connection to the City system. It will be tied in and then water services will be replaced. New storm drains will be installed in intersections.
  • Getty Tank: Blasting and painting will continue and the driveway to the tank from the cemetery will be completed

 

The Getty Tank after sandblasting and primer coating portions of the tank

 

A new gravel roadway replacing the old two track to the tank

 

Amsterdam, looking west from Sanford after the water main was installed

 

New gravel road bed installed on Sanford north of Norton

 

Despite the poor air quality, many dedicated construction workers continue to work through the heat and smoke to make improvements to the drinking water system and road network in Muskegon Heights:

Progress Report

  • Broadway: The remainder of the roadway was paved with the first courses of asphalt this week. THE ROAD IS STILL CLOSED TO ALL TRAFFIC.
  • Broadway: Manhole and valve structures were excavated and are being adjusted to the proper height in the asphalt that was paved last week.
  • Delano Avenue: Underground utility work is nearly complete, and work is moving toward restoration with concrete sidewalk, ramps and curb and gutter being installed.
  • Sanford Street: Work is being done to prepare for road reconstruction next week. This will involve grading and road gravel installation.
  • Oakwood Avenue: Water main connections are taking place along Oakwood between Glade and Mona. Many connections are complete.
  • Amsterdam Avenue: Water main installation has begun from 6th Street to east of 5th Street. The remaining portion of the original road, installed over 100 years ago, was removed.
  • Getty Tank: The sandblasting shroud was installed, and paint removal has begun. Recoating of the interior has begun, along with other minor improvements to the tank.
  • Lead Service Lines continue to be replaced throughout the City

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue

Upcoming Work Planned for Next Few Weeks:

  • Broadway: All remaining concrete restoration should be complete soon. Manhole and valve structures will be raised in the new asphalt. Final restoration should be done before the end of July.
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program. This work will dramatically increase in the next week or two through August.
  • Delano: Road and lawn restoration is taking place in Delano between Reynolds and Getty after all the underground work.
  • Sanford: The new roadway will be reconstructed, and concrete curb and gutter, driveway approaches and sidewalks will begin to be installed late next week or early the week of July 27
  • Oakwood: Water main connections will continue
  • Amsterdam: Water main installation will continue from 5th Street to Sanford. Testing will begin next week before putting it into service and new service connections are completed.
  • Getty Tank: New paint will be applied, and a new driveway will be constructed from the cemetery.
The Getty Water Tank – Photo taken before the smoke – hidden under the sandblasting shroud

 

New water main being installed in Amsterdam, looking east from 6th Street

 

Removal of the remainder of the old concrete in Amsterdam that was placed over 100 years ago

 

Broadway paved! Looking east from just west of Temple

 

Valves and manholes adjusted and raised for the final layer of asphalt at 7th and Broadway

Progress Report

  • Broadway: The first asphalt was paved yesterday between 5th and 9th Streets!
  • Broadway: All underground utility work is complete. Concrete curb and gutter, sidewalks, driveway approaches and sidewalk ramps are done from 5th to 9th and between Temple and Glade. Lawn restoration has begun already in most places along the route.
  • Delano Avenue: Utility work remains at the following intersections: Jarman, Ray and Riordan. Paving has begun on Delano at alley intersections with the first course.
  • Sanford Street: All underground utility work is completed. A few water services remain to be connected to the new water main.
  • Oakwood Avenue: Water main connections are taking place along Oakwood between Glade and Mona. New water main is installed in Cleveland between Glade and the first ally east.
  • Amsterdam Avenue: Pavement removal has begun and water main removal has begun
  • Getty Tank: The tank had rigging installed for the shrouding for the old paint removal. The interior has been blasted and is being prepped for new coatings
  • Lead Service Lines continue to be replaced throughout the City

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue

 

Upcoming Work Planned for Next Few Weeks:

  • Broadway: Concrete work will be completed between 9th and Temple in the next week. Manhole structures will be raised in the new asphalt section between 5th and 9th. Gravel grading will take place between 9th and Glade in preparation of the next round of paving.
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
  • Delano: Water main connections will take place at Ray, Jarman and Riordan. The last few intersections will be rebuilt and concrete curb and gutter and sidewalk ramps will be poured next week at nearly all the remaining intersections.
  • Sanford: The old water main will be taken out of service on Monday, July 13. The last few water services will be connected and road building will begin next week with cutting the sand for gravel road base to be installed
  • Oakwood: Water main connections will continue to occur and residents may have temporary water disruptions in the area between Norton and Broadway and Glade and Mona while these water main connections are taking place.
  • Amsterdam: Water main installation may begin later next week after additional pavement removals
  • Getty Tank: Once the containment shroud is installed, blasting will begin removing the old paint and new painting may begin on the tank

 

The first section of asphalt being done on this phase of Broadway at 9th Street looking east

 

Crews working in the heat pouring concrete sidewalk at the NE corner of Temple and Broadway

 

Rigging installed on the Tank at Getty Street getting ready for the protective shroud to be installed

Progress Report

  • Broadway: All underground utility work is nearly complete.
  • Broadway: Crews continue to install underdrain and road gravel base to get ready for more concrete curb and sidewalk
  • Delano Avenue: Just a few intersections remain for underground work. Crews are preparing to make asphalt restoration.
  • Sanford Street: New water main pipe has been installed and tied in from Norton to Oakwood and in Maplewood between Sanford and Jefferson. Customers are being connected to the new water main.
  • Norton Avenue: A new 18-inch valve was successfully installed on a major water transmission main near Peck Street
  • Oakwood Avenue: Crews are getting portions of the pavement removed for water main connections along Oakwood between Glade and Mona. Also, a new water main will be installed in Cleveland between Glade and Lemuel.
  • Amsterdam Avenue: Crews are getting ready to remove pavement for a full reconstruction of the roadway with new water main between 6th Street and Sanford Street.
  • Getty Tank: The tank was being washed this week in preparation of a new paint job

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue

Upcoming Work Planned for Next Few Weeks:

  • Broadway: Road reconstruction, along with sidewalks, curb and gutter is ongoing through the entire corridor.
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
  • Delano: Water main connections will take place at Jarman this week and work will move over to Ray Street intersection
  • Delano: Intersections at alleys and at Howden and Wood will be rebuilt with gravel and concrete curb and gutter. Asphalt road restoration is likely in some areas before Independence Day
  • Sanford: Water services are being connected to the new water mains. New storm drains will be installed/replaced at the same time.
  • Oakwood: Water main connection work will begin next week at Cleveland and Glade and then progress down Oakwood between Glade and Mona.
  • Getty Tank: Repainting will begin with a very large containment shroud being installed for protection while the old paint is blasted off before the tank can be repainted

 

An old drainage structure with its replacement on Norton near Peck Street

 

Old water main valves removed from the system

 

New curb and gutter being installed on Broadway

 

The last sanitary sewer and underground utility work on Broadway near Temple

Progress Report

  • Broadway: All water mains are now installed, and all water customers are connected to the new water mains.
  • Broadway: Crews are working on replacing the sanitary sewer main in Broadway between Temple and Waalkes.
  • Broadway: Crews continue to install underdrain and road gravel base between 6th and Park Streets
  • Delano Avenue: Underground utility work is complete in many alleys and in Howden and Wood Street intersections.
  • Sanford Street: New water main pipe has been installed from Norton to Oakwood and in Maplewood between Sanford and Jefferson.
  • Norton Avenue: A new 18-inch valve was successfully installed on a major water transmission main near Peck Street

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue

Upcoming Work Planned for Next Few Weeks:

  • Broadway: Crews should complete the remaining sanitary and storm sewer replacement work this upcoming week.
  • Broadway: Road reconstruction, along with sidewalks, curb and gutter is ongoing through the entire corridor.
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
  • Delano: Water main connections will take place at Jarman this week and work will move over to Ray Street intersection
  • Delano: Intersections at alleys and at Howden and Wood will be rebuilt with gravel and concrete curb and gutter. Asphalt road restoration is likely in some areas before Independence Day
  • Sanford: Water services will be replaced to the new water mains. New storm drains will be installed/replaced at the same time.
  • Oakwood: Water main connection work will begin next week at Cleveland and Glade and then progress down Oakwood between Glade and Mona. Pavement removals will begin next week.
  • Getty Tank: Repainting will begin with a very large containment shroud being installed for protection while the old paint is blasted off before the tank can be repainted

 

New 18-inch transmission main valve installed in Norton Avenue near Peck Street:

Broadway: Gravel road base is installed and some sidewalks have been installed. Looking west at 6th Street:

Broadway: Gravel road base is installed and some sidewalks have been installed. Looking east at 6th Street:

Old storm drain pipe removed in Maplewood between Sanford and Jefferson:

New storm drain pipe ready for installation after the water main is installed in Sanford, north of Maplewood:

Progress Report

  • Broadway: All water mains are now installed, and all water customers are connected to the new water mains.
  • Broadway: Crews continue to install underdrain and road gravel base between 5th and 9th Streets
  • Delano Avenue: New water main and storm drains were installed in the intersection of Superior. New valves were added to the 14-inch transmission main.
  • Sanford Street: New water main pipe has been installed from Norton to Oakwood and in Maplewood between Sanford and Jefferson.

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue

Upcoming Work Planned for Next Few Weeks:

  • Broadway: Roadway restoration work will continue between 9th and 5th Streets with underdrain installation and gravel road base installation
  • Broadway: Storm drains will be installed in several intersections
  • Broadway: Sanitary sewer main will be replaced between Waalkes and Temple
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
  • Delano: Water main connections will take place in the intersections of Howden and Wood next week. Expect some water disruptions in this area.
  • Delano: Storm drains will be replaced in several intersections
  • Sanford: New water mains will be tested and connected later in the week.
  • Norton: New valve will be added to the 18-inch water transmission main at Peck Street
  • Getty Tank: Repainting will begin with a very large containment shroud being installed for protection while the old paint is blasted off before the tank can be repainted
FIVE Lead Goosenecks on ONE service line on Peck Street! All removed and replaced with copper

 

Crews installing a 14-inch insertion valve on Hackley at Baker Street

 

Crews backfilling over top new water main in Maplewood Avenue between Jefferson and Sanford

 

Progress Report

  • Broadway: All water mains are now installed. Water services are nearly complete. Only a few remain to be replaced to the new water main.
  • Broadway: Crews continue to install underdrain and road gravel base between 5th and 9th Streets
  • Delano Avenue: New water main and storm drains were installed in the intersection of Dyson. A water main reconnection was made at Keating near McIlwraith that was discovered to be disconnected since 1975.
  • Sanford Street: New water main pipe has been installed from Norton to Maplewood.

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue

 

Upcoming Work Planned for Next Few Weeks:

  • Broadway: Roadway restoration work will continue between 9th and 5th Streets with underdrain installation and gravel road base installation
  • Broadway: The last remaining water services will be connected to the new water main
  • Broadway: Storm drains will be installed in several intersections
  • Broadway: Sanitary sewer main will be replaced between Waalkes and Temple
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
  • Delano: Additional water main connections will take place east of McIlwraith Street
  • Delano: Storm drains will be replaced in several intersections
  • Sanford: New water main will continue to be installed between Maplewood and Oakwood
  • Getty Tank: Repainting will begin with a very large containment shroud being installed for protection while the old paint is blasted off before the tank can be repainted
Sanford looking north from Maplewood

 

Crews are removing an old storm manhole that has an old water main running through it. The water main is being relocated and replaced further away from the sewer.

 

Broadway: Tying in new water main at Waalkes