City of Muskegon Heights - 2026 Road & Water Main Construction

Important Information

The work will involve replacement of water mains, valves, hydrants, and water services in the street, including new road where the water main is reconstructed. New ramps and sidewalks will also be constructed where they are disturbed for the work.

! Please visit our lead service line replacement dashboard to see the work that is left to be done.

Garbage Service:
Customers are encouraged to add a piece of tape to their cart and to clearly write their address on their cart. Service will remain and the Contractor will assist with getting your cart picked up and returned on your regular garbage days if the road in front of your home or business is inaccessible to garbage trucks.

Mail Service:
Post deliveries will be maintained throughout the project.

Access/Traffic:
Work will result in full closure within the construction areas as noted on the map shown. Follow the updates for specific closure dates. Broadway Avenue detour will be Glade to Summit to Peck Street.  Temple and 6th Streets will be open as much as possible to cross Broadway. Otherwise, all other side streets will be closed at Broadway. Thru traffic will be prohibited in all construction areas.

 

1. Broadway, Phase 3 – Glade to 5th Street

Project Timeframe: March 2, 2026 – Labor Day 2026
Contractor: McCormick Sand of Twin Lake, MI
24- hour Emergency Number: Rob Murphy, 231.740.8894
City Contacts:
John Allen, Utilities Director
231) 955-0050
Khi Guy, Public Works Director
(231) 332-6762
Primary Project Contact:
Metro Consulting Associates
Ashwini Tapase, (313) 410-9384
Prein&Newhof Contact:
Matt Hulst, (231) 799-9093

 

2. Delano, Reynolds to Getty

Project Timeframe:  Mid April 2026 – August 2026
Contractor: Terra Contractors of Muskegon, MI
24-hour Emergency Number:
Jason Franklin, (231) 206-7030
Primary Project Contact:
Dan Sorek, (616) 218-2940

 

3. Sanford, Phase 2 – Oakwood to Norton and Maplewood, Jefferson to Sanford

Project Timeframe: Late April, 2026 – August 2026
Contractor: Jackson-Merkey Contractors of Muskegon, MI
Primary Project Contact:
Dan Sorek, (616) 218-2940

 

4. Oakwood, Glade to Mona

Project Timeframe: Summer 2026 – Fall 2026
Contractor: McCormick Sand of Twin Lake, MI
24- hour Emergency Number:
Rob Murphy, (231) 740-8894
Primary Project Contact:
Dan Sorek, (616) 218-2940

 

5. Norton, Park to Peck

Project Timeframe: Summer 2026 – Fall 2026
Contractor: McCormick Sand of Twin Lake, MI
24- hour Emergency Number:
Rob Murphy, (231) 740-8894
Primary Project Contact:
Dan Sorek, (616) 218-2940

 

6. Amsterdam, 6th to Peck

Project Timeframe: Summer 2026 – Fall 2026
Contractor: McCormick Sand of Twin Lake, MI
24-hour Emergency Number:
Rob Murphy, (231) 740-8894
Primary Project Contact:
Dan Sorek, (616) 218-2940

 

7. Getty Water Tank Repainting

Project Timeframe: May 2026 – August 2026
Contractor: Seven Brothers Painting of Shelby Township, MI
Primary Project Contact:
Peter Brink, (231) 798-0101

 

8. Water Filtration Plant and Low Lift Pump Station Improvements

Project Timeframe: March 2026 – 2027
Contractor: Franklin Holwerda Company of Wyoming, MI
Primary Project Contact:
Peter Brink, (231) 798-0101

Projects
  1. Broadway, Phase 3 COMPLETE!
  2. Delano, Reynolds to Getty COMPLETE!
  3. Sanford, Phase 2 COMPLETE!
  4. Oakwood, Glade to Mona
  5. Norton, Park to Peck
  6. Amsterdam, 6th to Peck
  7. Getty Water Tank Repainting
  8. Water Filtration Plant and Low Lift Pump Station Improvements (2323 Seminole Rd, not mapped)

Progress Report

  • Broadway: All water mains are now installed, and all water customers are connected to the new water mains.
  • Broadway: Crews continue to install underdrain and road gravel base between 5th and 9th Streets
  • Delano Avenue: New water main and storm drains were installed in the intersection of Superior. New valves were added to the 14-inch transmission main.
  • Sanford Street: New water main pipe has been installed from Norton to Oakwood and in Maplewood between Sanford and Jefferson.

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue

Upcoming Work Planned for Next Few Weeks:

  • Broadway: Roadway restoration work will continue between 9th and 5th Streets with underdrain installation and gravel road base installation
  • Broadway: Storm drains will be installed in several intersections
  • Broadway: Sanitary sewer main will be replaced between Waalkes and Temple
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
  • Delano: Water main connections will take place in the intersections of Howden and Wood next week. Expect some water disruptions in this area.
  • Delano: Storm drains will be replaced in several intersections
  • Sanford: New water mains will be tested and connected later in the week.
  • Norton: New valve will be added to the 18-inch water transmission main at Peck Street
  • Getty Tank: Repainting will begin with a very large containment shroud being installed for protection while the old paint is blasted off before the tank can be repainted
FIVE Lead Goosenecks on ONE service line on Peck Street! All removed and replaced with copper

 

Crews installing a 14-inch insertion valve on Hackley at Baker Street

 

Crews backfilling over top new water main in Maplewood Avenue between Jefferson and Sanford

 

Progress Report

  • Broadway: All water mains are now installed. Water services are nearly complete. Only a few remain to be replaced to the new water main.
  • Broadway: Crews continue to install underdrain and road gravel base between 5th and 9th Streets
  • Delano Avenue: New water main and storm drains were installed in the intersection of Dyson. A water main reconnection was made at Keating near McIlwraith that was discovered to be disconnected since 1975.
  • Sanford Street: New water main pipe has been installed from Norton to Maplewood.

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue

 

Upcoming Work Planned for Next Few Weeks:

  • Broadway: Roadway restoration work will continue between 9th and 5th Streets with underdrain installation and gravel road base installation
  • Broadway: The last remaining water services will be connected to the new water main
  • Broadway: Storm drains will be installed in several intersections
  • Broadway: Sanitary sewer main will be replaced between Waalkes and Temple
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
  • Delano: Additional water main connections will take place east of McIlwraith Street
  • Delano: Storm drains will be replaced in several intersections
  • Sanford: New water main will continue to be installed between Maplewood and Oakwood
  • Getty Tank: Repainting will begin with a very large containment shroud being installed for protection while the old paint is blasted off before the tank can be repainted
Sanford looking north from Maplewood

 

Crews are removing an old storm manhole that has an old water main running through it. The water main is being relocated and replaced further away from the sewer.

 

Broadway: Tying in new water main at Waalkes

The weather is looking more like summer in Michigan! Construction is progressing nicely on several projects in Muskegon Heights.  Be sure to visit the new splash pad at Rowan Park in Downtown Muskegon Heights to cool off!

Just a quick update on work happening recently during this past week.

Progress Report

  • Broadway: All water mains are now installed. Water services are nearly complete. Only a few remain to be replaced to the new water main.
  • Broadway: Crews have been installing underdrain and road gravel base between 5th and 9th Streets
  • Painting crews mobilized to begin painting the water tank on Getty
  • Delano Avenue: Water main connections were made in several alleys and hydrants have been installed and replaced
  • Sanford Street: Pavement has been removed between Oakwood and Norton and on Norton between Sanford and Peck and on Maplewood between Jefferson and Sanford

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue

Upcoming Work Planned for Next Few Weeks:

  • Broadway: Roadway restoration work will continue between 9th and 5th Streets with underdrain installation and gravel road base installation
  • Broadway: The last remaining water services will be connected to the new water main
  • Broadway: Storm drains will be installed in several intersections
  • Broadway: Sanitary sewer main will be replaced between Waalkes and Temple
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
  • Delano: Additional water main connections will take place east of McIlwraith Street
  • Delano: Storm drains will be replaced in several intersections
  • Sanford: New water mains will begin to be installed between Oakwood and Norton on Monday – This is a continuation of the project that was completed last year.
Broadway Avenue, looking west from 6th Street
Broadway, looking east from Temple

 

An old brick drainage structure in Broadway that needs to be replaced (before/during/after):

 

Progress Report

  • Broadway: All water main is now installed.
  • Broadway: Sanitary sewer manholes are installed in intersections up to 9th Street
  • Broadway: Crews were preparing to install underdrain and prepare the road for gravel road base between 5th and 9th Streets
  • Painting crews mobilized to begin painting the tank soon
  • Delano Avenue: Water main connections were made in several locations along Delano
  • Crews began preparations to begin work on Sanford Street between Norton and Oakwood next week

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

Upcoming Work Planned for Next Few Weeks:

  • No work will take place on Monday, May 25, 2026, due to Memorial Day Holiday
  • Broadway: Roadway restoration work will begin between 9th and 5th Streets with underdrain installation and gravel road base installation
  • Broadway: The last remaining water services will be connected to the new water main
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
  • Delano: Additional water main connections will take place east of Wood Street
  • Delano: Storm drains will be replaced in several intersections
  • Sanford: Detours and traffic controls will be installed and the pavement will be removed next Wednesday

 

Another new hydrant was installed on Delano Avenue

Here is another weekly update on the recent work performed in Muskegon Heights on water main and road improvements.

Progress Report

  • Broadway: All water main is now installed. The last section between Temple and 9th Street is undergoing testing before it can be connected to the existing system next week.
  • Broadway: Sanitary sewer manholes are being replaced in intersections
  • Broadway: Crews were preparing to install underdrain and prepare the road for gravel road base between 5th and 7th Streets
  • The temporary cell tower near the Getty Tank is up and running and the equipment is off of the Tank. The tank repainting will begin soon.
  • Delano Avenue: Water main connections were made in several locations along Delano

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

Upcoming Work Planned for Next Few Weeks:

  • Broadway: Sanitary sewer manholes will be replaced in the intersections of 9th and 8th Streets and the sewer main will be replaced between Temple and Waalkes
  • Broadway: Water main will be connected to the new system and the last few water services will be replaced between Temple and 9th Streets
  • Broadway: Storm drain work will take place between 9th and 5th Streets
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
  • Additional water main connections will take place down Delano east of Wood Street
  • Storm drains will be replaced in the intersections of Delano and Howden and Wood
  • Water main replacement and road improvements will begin soon on Sanford Street between Oakwood and Norton, and on Maplewood between Sanford and Jefferson

 

Crews installing a new sanitary sewer manhole at Broadway and 7th

 

Crews protecting existing utilities in the intersection of Broadway and 7th

 

Crews installing a new fire hydrant on Delano

Progress Report:

  • Broadway: Sanitary sewer manholes have been replaced and improvements made to drainage for the 7th Street Intersection
  • Broadway: Crews were preparing to install underdrain and prepare the road for gravel road base between 5th and 7th Streets
  • A temporary cellular tower is being installed next to the Getty water tank so that the cellular antenna can be removed from the tank and relocated to the temporary tower so the tank can be repainted next month
  • Delano Avenue: Numerous new taps were made on the main in Delano in preparation for connecting more water mains to that transmission water main in Delano

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

Upcoming Work Planned for Next Few Weeks:

  • Water main connections will happen on Monday, May 11, 2026 at the intersection of Howden and Delano. This will cause a disruption in water to roughly 85 customers in the following areas:
    • 2000-2200 Blocks of Howden
    • 2000 Block of Riordan
    • 2100 Block of Reynolds
    • Several addresses along Delano between Reynolds and Getty
  • Water main connections are tentatively scheduled for Tuesday May, 12, 2026 at the intersection of Wood and Delano. This will cause a disruption in water to roughly 30 customers in the 2000-2100 Blocks of Wood street and several addresses along Delano between Howden and Getty.
  • Sanitary sewer manholes will be replaced in the intersections of Broadway between 9th and 8th Streets
  • Additional water main work will occur on 6th Street between Manahan and Sherman
  • Storm drain work will take place on Broadway between 9th and 5th Streets
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
  • Additional water main connections will take place down Delano east of Wood Street
  • Storm drains will be replaced in the intersections of Delano and Howden and Wood after the water main is connected
New sanitary sewer manhole at Broadway and 7th Street

 

The base for the temporary cellular antenna being installed next to the Getty water tank

 

New water main taps on the transmission main in Delano ready for connection

 

Looking up from the old manhole that was removed from Broadway and 7th Street

 

Progress Report

  • Broadway, Glade to Temple: Underground utilities are complete. Road gravel base has been installed. Concrete curb and gutter and sidewalk has been installed on the north side of the road.
  • Broadway, 9th to 5th: Water main is complete and all tie ins and water services are connected to the new mains. Sanitary sewer manholes are being replaced, starting at 6th Street and working west to 9th Street.
  • Delano Avenue: New water main is installed in the intersections of Howden and Wood Streets. These new water mains will be connected after they are tested. Planned testing will be next week and the connections will likely be the week after.

 

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

 

Upcoming Work Planned for Next Few Weeks:

  • Sanitary sewer manholes will be replaced in the intersections of Broadway between 9th and 7th Streets
  • Additional water main work will occur on 6th Street between Manahan and Sherman
  • Storm drain work will take place on Broadway between 9th and 5th Streets
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
  • Additional water main connections will take place down Delano east of Wood Street
  • Storm drains will be replaced in the intersections of Delano and Howden and Wood after the water main is connected

 

New sanitary sewer manhole at the intersection of Broadway and 6th

 

Old Hydrant from the corner of 6th & Broadway removed

 

Old water main removed from the intersection of Broadway and 6th

 

Condition of Broadway near Lemuel, looking west

More progress to report this week on the water main and road improvements in the City of Muskegon Heights.

Progress Report

  • The new water main and storm drains are installed in Broadway between Glade and Temple. The gravel road base has been installed and the team is getting ready to begin installing concrete curb and sidewalk next week on the north side of Broadway here.
  • The new water main is installed in Broadway between 9th Street and 5th Street with connections to the existing system at 7th Street, 8th Street, and 9th Street.  Customers are being connected to the new water main between 9th and 5th Streets.
  • Pavement removals took place on Delano Avenue between Reynolds and Getty Streets for water main improvements in the intersections
  • New water main is being installed in the intersection of Howden and Delano. This is the ONLY intersection on Delano that is closed. All other intersections are currently open to traffic. The contractor will only be closing one intersection at a time. Please use the posted detour of Reynolds to Hackley to Getty to get around any closed intersections of Delano Avenue.

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

Upcoming Work Planned for Next Few Weeks:

  • Water mains will be tied in at Broadway and 6th Street on Monday, April 27, 2026. This will mean a temporary water disruption for all customers on 6th Street between Summit and Sherman between 8 AM and 4 PM.  Water should be turned back on before the end of the day. If the water is cloudy, that is air trapped in the lines. Please be sure to flush all of your water fixtures and clean the aerators on your faucets. It is best to flush the Cold water in a bathtub first because there is typically no aerator there, and it will move the most water. Be sure to remember to flush outside spigots as well now that the weather is improving.
  • Sanitary sewer manholes will be replaced in the intersections of Broadway between 9th and 5th Streets
  • Additional water main work will occur on 6th Street between Manahan and Sherman
  • Storm drain work will take place on Broadway between 9th and 5th Streets
  • Water service lines will be replaced on Broadway between 8th and 5th Streets
  • Concrete curb and gutter and sidewalk will be installed on the north side of Broadway between Glade and Temple starting Monday, April 27, 2026. Access to businesses will be CLOSED for the entire week to allow for the concrete to cure before traffic can be allowed to drive over the concrete.
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
  • Storm drains will be replaced in the intersection of Howden and Delano after the water main is replaced.
  • Water main will be replaced in the intersection of Wood and Delano after the work in Howden is complete. The contractor will ‘leap frog’ every other intersection and then go back and finish each so that there are not 2 intersections closed at one time on Delano until paving operations.

 

Crews tapping an 18-inch water main for a new fire hydrant at 6th and Columbia:

Progress Report

  • The new water main is installed in Broadway between Glade and Temple. Customers are connected to the new water main in this location, and it is tied to the existing system and in service.
  • The new water main is installed in Broadway between 9th Street and 5th Street with connections to the existing system at 6th Street, 7th Street, and 8th Street.  Customers are being connected to the new water main between 9th and 5th Streets.
  • Storm drains are being replaced between Glade and Temple.
  • Traffic control and preparations are being made for water main work on Delano Avenue between Reynolds and Getty Streets

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

 

Upcoming Work Planned for Next Few Weeks:

  • Water mains will be tied in at Broadway and 9th Street on Monday, April 20, 2026. This will mean a temporary water disruption for all customers on 9th Street between Summit and Sherman between 8 AM and 4 PM.  Water should be turned back on before the end of the day. If the water is cloudy, that is air trapped in the lines. Please be sure to flush all of your water fixtures and clean the aerators on your faucets. It is best to flush the Cold water in a bathtub first because there is typically no aerator there, and it will move the most water. Be sure to remember to flush outside spigots as well now that the weather is improving.
  • Sanitary sewer manholes will be replaced in the intersections of Broadway between 9th and 5th Streets
  • Additional water main work will occur on 6th Street between Summit and Sherman, with 2 new hydrants and some water connections to eliminate an old water main on 6th Street
  • Storm drain work will take place on Broadway between 9th and 5th Streets
  • Water service lines will be replaced between 8th and 5th Street
  • Roadway will begin to be shaped on Broadway between Temple and Glade Streets
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
  • Pavement removals for water main work on Delano between Reynolds and Ray Streets
  • Water main work will begin on Delano Avenue between Reynolds and Ray Streets with the connections to the large water main in the alleys and installation of new hydrants and valves

 

Looking west on Broadway from 9th Street towards Park Street. Businesses are open and accessible!

 

Looking south towards Broadway at 9th Street

 

Looking east on Broadway, just west of 6th Street. Businesses are open and access is available!

Progress Report

  • The new water main was tied in at Glade and Broadway to the existing system
  • A tie-in of the new water main in Broadway is also happening at 5th Street to the section built last year
  • Water services have been replaced to the new water main between Glade and Temple
  • New water main continues to be installed between Temple and 9th Streets in Broadway
  • The City has surpassed the halfway mark in its journey to removing the lead water service lines from the system!

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

Upcoming Work Planned for Next Few Weeks:

  • Water main will continue to be installed in Broadway between 9th and Temple
  • Water service lines will be replaced between 8th and 5th Street
  • Water service lines will be replaced between Temple and Glade
  • Storm drain work will begin between Glade and Temple
  • Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
  • Pavement removals for water main work on Delano between Reynolds and Ray Streets
Tie-in of new water main to the existing system