March 20, 2026
Construction is set to begin on March 30, 2026 on Stage 1 of this project. Closures will include 48th Ave from north of Port Sheldon St to south of Tyler St. Traffic on 48th Ave will utilize Port Sheldon St, 36th Ave, and Baldwin St.
The initial construction will be of sanitary sewer for J&H to tie-in to sanitary sewer north of Rush Creek. When the contractor is able, after constructing J&H’s sanitary sewer, they will start the construction of the water transmission main.
The Contractor will begin work on Stage 1 by installing the 24-inch water main under Rush Creek using a bore and jack. Once, the Rush Creek crossing is complete, the contractor will access and connect to the existing 24-inch water transmission main north of Port Sheldon St that was installed in 2025. Work will then continue north towards Tyler Street. Detour Map
The Contractor is anticipated to begin Stage 2 and cross Tyler St in mid-July. Closures will include 48th Ave from south of Tyler St to south of Baldwin St. Traffic will utilize Port Sheldon St, 36th Ave, 56th Ave, and Baldwin Street. Detour Map
Stage 3 will begin when the intersection of Baldwin St and 48th Ave is closed, and this is anticipated to begin in early August. Traffic will utilize Port Sheldon St, 36th Ave, 56th Ave, and Bauer Road. Detour Map
In addition to the Georgetown Charter Township water transmission main construction, Blendon Township is constructing a water main in Tyler St from 48th Ave to Tyler Pines Ave; J&H Oil is constructing a sanitary sewer in 48th Ave from Port Sheldon to north of Rush Creek; and the Ottawa County Road Commission will be constructing a roundabout at the intersection of 48th Ave and Baldwin St. These projects may have traffic impacts beyond what is listed here, but brief updates on the status of those projects will be posted here along with the water transmission main updates.
