Project Information

Contract No. 1: Construct force main from West Randall lift station in City of Coopersville to Ottawa County line.

Access/Traffic: Local traffic will be maintained during pipeline construction. There may be times when your driveway is inaccessible because pipeline construction is occurring in front of your house or driveway restoration is taking place. The contractor will work with you ahead of time and will make special access arrangements with you if needed.

Mail: Mailboxes that interfere with pipeline construction will be temporarily relocated so that mail service can be maintained during construction. If your mailbox needs to be temporarily relocated, the contractor will inform you of where it has been moved to and when they anticipate it will be returned to its original location.

Garbage Pickup: The contractor will work with you and your waste hauler to maintain service throughout construction. If pipeline construction interferes with your waste haulers ability to pick up your garbage, the contractor will temporarily move your garbage bins to a central location and return them to the end of your driveway by the end of the work day.

Contact

Prein&Newhof – Field
Brad Kuiper
(616) 485-0286
bkuiper@preinnewhof.com

Contractor
Milbocker & Sons
(269) 673-2195

Muskegon County
(231) 724-3440

Work completed/in progress:

  • Installed approximately 2,000 feet of force main

Anticipated work activities for the coming week:

  • Resume pipe fusing and begin preparing for second leakage test of the installed force main.

Work completed/in progress:

  • Installed approximately 1,500 feet of force main
  • Repair drain tile damaged during force main installation

Anticipated work activities for the coming week:

  • Resume pipe fusing.
  • Continue laying pipe west of 72nd Avenue.

Work completed/in progress:

  • Crossed 72nd Avenue and restored road and farmland east of 72nd.
  • Began laying pipe west of 72nd Avenue.

Anticipated work activities for the coming week:

  • Continue laying pipe west of 72nd Avenue.

**72nd Avenue between Cleveland Street and State Road will be closed starting March 31. The anticipated closure will last approximately 1 month.**

Work completed/in progress:

  • Installed approximately 1,100′ of force main installed along Railroad corridor up to 72nd Avenue.
  • Preparing site west of 72nd Avenue for pipeline installation.
  • Flowable filled the casing beneath the former Railroad bed.
  • Continued fusing lengths of HDPE pipeline.

Anticipated work activities for the coming week:

  • Continue fusing lengths of HDPE pipeline.
  • Resume pipe laying on north side of Railroad corridor toward 72nd Avenue.

Work completed/in progress:

  • 600 feet of pipe installed along Railroad corridor west of 68th Avenue and pipe installed through casing beneath Railroad
  • Continued fusing lengths of HDPE pipeline.

Anticipated work activities for the coming week:

  • Continue fusing lengths of HDPE pipeline.
  • Resume pipe laying on north side of Railroad corridor toward 72nd Avenue.

Work completed/in progress:

  • Hydrostatic pressure test for first segment of pipe passed.
  • 600′ of pipe installed along Railroad corridor west of 68th Avenue
  • Continued fusing lengths of HDPE pipeline.

Anticipated work activities for the coming week:

  • Continue fusing lengths of HDPE pipeline.
  • Resume pipe laying west of 68th Avenue along the Railroad corridor.

Work completed/in progress:

  • Dug and replaced poor joint near 64th Avenue.
  • Continued fusing lengths of HDPE pipeline.
  • Prepared for pressure test.

Anticipated work activities for the coming week:

  • Perform pressure test.
  • Continue fusing lengths of HDPE pipeline.
  • Resume pipe laying west of 68th Avenue along the Railroad corridor.

Work completed/in progress:

  • Installed pipe through casing beneath 68th Avenue.
  • Installing restraint collar and air release structure west of 68th Avenue.
  • Preparing pipe for pressure test.

Anticipated work activities for the coming week:

  • Dig up and replace poor joint near 64th Avenue.
  • Perform pressure test once joint is replaced.
  • Continue fusing lengths of HDPE pipeline.

Work completed/in progress:

  • Completed force main installation along Railroad corridor on north side of Continental property progressing toward 68th Avenue.

Anticipated work activities for the coming week:

  • Cross 68th Avenue and continue force main installation along Railroad corridor.
  • Prepare for first pressure test of force main.
Work completed/in progress:
  • Continued force main installation along Railroad corridor on north side of Continental property progressing toward 68th Avenue.
  • Flowable filled casings beneath the Railroad and adjacent to the electrical substation.
Anticipated work activities for the coming week:
  • Cross 68th Avenue and continue force main installation along Railroad corridor.
  • Prepare for first pressure test of force main.