West Randall Lift Station

Project Information

West Randall Lift Station: Construct a second lift station adjacent to the existing West Randall Lift Station to accommodate proposed flows for the Southeast Regional Force Main.

Contact

Prein&Newhof
Will Thies, PE
(616) 364-8491
wthies@preinnewhof.com

Contractor
Grand River Construction
(616) 669-5611

Muskegon County
(231) 724-3440

Work completed/in progress:

  • Metal roof installation continues.
  • Preparation for wet well lining complete.
  • Interior walls painted.

Anticipated work activities for the coming week:

  • Begin wet well coating.
  • Complete metal roof installation.
  • Pour equipment pads.

Work completed/in progress:

  • Dry well stair installation nearly completed.
  • Metal roof installation started.
  • Continue preparation for wet well lining.

Anticipated work activities for the coming week:

  • Continue roof construction and preparation for wet well lining.
  • Begin painting interior walls

Work completed/in progress:

  • Continued preparation for wet well lining, and dry well stair installation.
  • Block filler applied.

Anticipated work activities for the coming week:

  • Continue roof construction, preparation for wet well lining, and dry well stairs installation.
  • Install dry well ductwork and conduit.
  • Begin painting interior walls

Work completed/in progress:

  • Roof construction in progress
  • Preparation for wet well lining
  • Began dry well stairs

Anticipated work activities for the coming week:

  • Continue roof construction, preparation for wet well lining, and dry well stairs
  • Install dry well ductwork
  • Begin painting interior walls

Work completed/in progress:

  • Precast concrete plank ceiling was installed.
  • Roof trusses were placed.
  • Steel stair installation began.

Anticipated work activities for the coming week:

  • Steel stair installation will be completed.
  • Pump suction pipe installation will begin.

Work completed/in progress:

  • Masonry and conduit installation continued.
  • Drain and water lines were installed in the dry well.
  • Masonry work was completed.

Anticipated work activities for the coming week:

  • Precast concrete plank ceiling will be placed.

Work completed/in progress:

  • Masonry installation progressed. The interior walls and the north exterior wall are now complete.
  • Pump pads and wet well hatch curbs were poured.

Anticipated work activities for the coming week:

  • Masonry and drain pipe installation will continue.

Work completed/in progress:

  • Dry well drains and formwork were installed in preparation for pouring the dry well floor.
  • Electrical conduit installation began in the dry well.

Anticipated work activities for the coming week:

  • The dry well floor will be poured Monday.
  • Conduit installation will continue, and the masonry crew will begin mobilizing to construct the building walls.

Work completed/in progress:

  • Dry well lid forms have been stripped.
  • Electrical and mechanical crews are working on installation of conduit and drains in the dry well.

Anticipated work activities for the coming week:

  • Grand River Construction will pour the dry well floor, pump bases, and/or wet well access hatch curbs.

Work completed/in progress:

  • 48-inch and 42-inch sanitary sewer and manholes were installed.
  • The wet well lid forms were stripped.
  • Remaining conduit, floor sleeves, and top mat of steel were installed in the dry well lid.

Anticipated work activities for the coming week:

  • The dry well lid is scheduled to be poured Tuesday.
  • Installation of sanitary sewer will continue.