March 21, 2025
Work completed/in progress:
- The Diversion Chamber was placed, and 48-inch sewer installation began.
- Base mat of steel was installed in the dry well lid, and floor sleeves and conduit were added.
Anticipated work activities for the coming week:
- Remaining conduit and steel will be installed in the dry well. The dry well lid is scheduled to be poured late next week.
- Installation of underground structures and sewer will continue.