City of Wyoming - Water Transmission Main No. 3

Important Information

The City of Wyoming owns and operates the Donald K. Shine Drinking Water Plant located near Lake Michigan on New Holland Street. Water from Lake Michigan is pumped to the plant where it is treated and then distributed to thirteen communities serving over 250,000 people in Ottawa and Kent Counties.

The City and Ottawa County is embarking on a multi-year construction project to enhance this regional asset through construction of approximately 11 miles of pipeline. This project, funded by ratepayers from the customer communities, will improve the drinking water transmission system reliability and functionality for the entire region.

The project is expected to be completed over several years with multiple contractors coordinating their efforts. Kamminga & Roodvoets of Grand Rapids, Michigan and Ric-Man Construction of Sterling Heights, Michigan are the two general contractors entrusted to construct this pipeline.

A map depicting the project area and general schedule for the project can be viewed at the link below.

Access/Traffic:

Local traffic will be maintained during pipeline construction. There may be times when your driveway is inaccessible because pipeline construction is occurring in front of your house or driveway restoration is taking place. The contractor will work with you ahead of time and will make special access arrangements with you if needed.

Mail:

Mailboxes that interfere with pipeline construction will be temporarily relocated so that mail service can be maintained during construction. If your mailbox needs to be temporarily relocated, the contractor will inform you of where it has been moved to.

Garbage Pickup:

The contractor will work with you and your waste hauler to maintain service throughout construction. If pipeline construction interferes with your waste haulers ability to pick up your garbage, the contractor will temporarily move your garbage binds to a central location and return them to the end of your driveway by the end of the work day.

Contractor:

Kamminga & Roodvoets
Ric-Man Construction

City of Wyoming
waterprojects@wyomingmi.gov

Van Buren – Butternut to US-31

  • Van Buren from Butternut to US-31 is closed.
  • 144th Ave is scheduled to be re-paved today.
  • 164th Ave is closed between New Holland and Van Buren.
  • The final layer of asphalt on driveways between Butternut and 152nd is scheduled to be placed on August 25.
  • The first layer of asphalt is scheduled to be placed between 152nd Ave and 136th Ave next week.
  • Work on miscellaneous transmission main items will continue next week.
  • Work inside the pipe continues.

164th – New Holland to Van Buren

  • Pipe staging occurred this week and will continue next week.

Van Buren – US-31 to 96th Avenue

  • Van Buren from US-31 to 120th Ave is closed.
  • Preparations for the tunneling beneath US-31 and the Railroad continued. The tunneling operation is scheduled to begin today and will continue next week.
  • The pipe crew began installation of the valve vault east of 128th Avenue.

New Holland – 104th to 96th & Easement

  • New Holland Street from 104th Ave to 96th Ave is closed.
  • New Holland Street paving began August 19 and should be completed today.
  • Work continued on pipe appurtenances along Barry Street.

Van Buren – Butternut to US-31

  • Van Buren from Butternut to US-31 is closed.
  • 144th Ave, south of Van Buren, is closed. 144th Ave is scheduled to be re-paved on August 19.
  • 164th Ave is closed between New Holland and Van Buren.
  • Driveways have been replaced between Butternut and 152nd Ave.
  • Driveways between 152nd Ave and 144th Ave are scheduled to be re-paved on August 19.
  • Road building between 152nd Ave and 144th Ave continues this week. Road building between 144th Ave and 136th Ave will begin shortly.
  • Work on the valve vault at the southeast corner of Van Buren and 144th Ave is underway and will continue this week.
  • Pipe laying progressed eastward between 136th Ave and US-31. Pipe laying will be suspended temporarily until the tunneling operation is complete.
  • Work inside the pipe continues.

164th – New Holland to Van Buren

  • Road removal on 164th Ave occurred last week.
  • Pipe is scheduled to begin arriving this week.

Van Buren – US-31 to 96th Avenue

  • Van Buren from US-31 to 120th Ave is closed.
  • Preparations for the tunneling beneath US-31 and the Railroad continued. The tunneling operation is scheduled to begin later this week.
  • The pipe crew remobilized and will recommence pipe laying this week. Work will start at a valve vault east of 128th Avenue.

New Holland – 104th to 96th & Easement

  • New Holland Street from 104th Ave to 96th Ave is closed.
  • Work continued on restoration within New Holland. Paving is scheduled for this week of August 17.
  • Work began on pipe appurtenances along Barry Street.
  • Excess soils north of Barry Street may begin being hauled off-site.

Van Buren – Butternut to US-31

  • Van Buren from Butternut to US-31 is closed.
  • The intersection of Van Buren and 136th Ave has been reopened.
  • 144th Ave, south of Van Buren, is closed.
  • Starting August 10, 164th Ave will be closed between New Holland and Van Buren.

 

  • Restoration work continued between 160th Ave and 152nd Avenue. The area has been topsoiled and seeded.
  • Road building between 152nd Ave and 144th Ave has begun and will continue next week.

 

  • Pipe laying progressed eastward from west of 144th Ave beneath the Harlem Drain and 144th Avenue. Work on the valve vault at the southeast corner of Van Buren and 144th Ave is underway and will continue next week.
  • Pipe laying progressed eastward between 136th Ave and US-31. Pipe laying will continue next week.
  • Work inside the pipe continues.

 

164th – New Holland to Van Buren

  • Road removal on 164th Ave will occur on August 10. Pipe will begin arriving on August 17.

 

Van Buren – US-31 to 96th Avenue

  • Van Buren from US-31 to 120th Ave is closed.
  • Preparations for the tunneling beneath US-31 and the Railroad continue.
  • Pipe laying is expected to resume late next week or the following week.

 

New Holland – 104th to 96th & Easement

  • New Holland Street from 104th Ave to 96th Ave is closed.
  • Work continued on restoration within New Holland. Paving is scheduled for the week of August 17.
  • The last piece of transmission main pipeline for this area was placed this week.
  • Restoration work will continue next week, as well as work on pipe appurtenances along Barry Street.

Link to presentation slides from July 29 meeting: 164th Ave Open House Presentation

  • Van Buren Street from Butternut to US-31 is closed.
  • The intersection of Van Buren Street and 136th Avenue is closed and is scheduled to be paved and reopened today. Some driveway paving may be completed.
  • 144th Avenue, south of Van Buren, is scheduled to be closed starting this afternoon in preparation for pipeline installation. Closure is expected to last 2-3 weeks.
  • Restoration work continued between 160th and 152nd. Road reconstruction between 144th Avenue and 136th Avenue will begin soon.
  • Various pipe, structure, and culvert installation occurred this week within the closure area.
  • Next week pipe laying will resume at the 144th Avenue crossing and east of 136th Avenue.
  • Work inside the pipe continues.

 

  • On August 29, the city held an informational meeting for residents along 164th Avenue. 164th Avenue is scheduled to close the week of August 10. Next week, K&R may begin some exploratory work along 164th Avenue in preparation for pipe laying.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • Preparations will continue next week for the tunneling beneath US-31 and the Railroad.
  • Pipe laying is expected to resume mid-August.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Work continued on restoration within New Holland Street.
  • Work in New Holland Street will continue next week in preparation for paving.
  • Van Buren Street from Butternut to US-31 is closed.
  • The intersection of Van Buren Street and 136th Avenue is closed and is scheduled to be paved on July 30 and reopened on July 31.
  • 144th Avenue, south of Van Buren, is scheduled to be closed starting July 31 for pipeline installation.
  • Restoration work continued between 160th and 152nd. Road reconstruction between 144th Avenue and 136th Avenue will begin soon.
  • Pipe laying between 152nd and 144th Avenue has progressed to the 144th Avenue crossing. The 144th Avenue crossing is scheduled to begin after the road closing on July 31. The crossing will take approximately two weeks.
  • Pipe laying between 144th and 136th Avenue has progressed through the 136th Avenue intersection.
  • This week, both pipe crews will be working primarily on hydrants, air valve assemblies, and other appurtenances along the pipeline.
  • Work inside the pipe continues.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • Preparations will continue this week for the tunneling beneath US-31 and the Railroad.
  • Pipe laying is expected to resume near the end of July.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Work continued on restoration within New Holland Street.
  • Work in New Holland Street will continue this week in preparation for paving.
  • Van Buren Street from Butternut to US-31 is closed.
  • The intersection of Van Buren Street and 136th Avenue will be closed starting July 20 for pipeline installation across the intersection. The intersection closure is anticipated to last no more than two weeks.
  • The first layer of asphalt between 160th and 152nd was paved on Monday, July 13.
  • Pipe laying between 152nd and 144th Avenue has progressed to approximately 1,000′ west of 144th.
  • Pipe laying between 144th and 136th Avenue has progressed to approximately 400′ west of 136th Avenue.
  • Pipe laying will continue with both crews next week.
  • Work inside the pipe continues.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • Pipe was staged near US-31 for the upcoming tunneling operation beneath the highway. Additional tunneling equipment and materials may begin arriving next week.
  • Pipe laying is expected to resume near the end of July.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Work continued on various pipe appurtenances within New Holland Street.
  • Work in New Holland Street will continue next week in preparation for paving the week of July 27.
  • Van Buren Street from Butternut to US-31 is closed.
  • Road building between 160th and 152nd continued. Paving for this length of road is scheduled for Monday, July 13!
  • Pipe laying between 152nd and 144th Avenue has progressed to approximately 2,000′ west of 144th.
  • Pipe laying between 144th and 136th Avenue has progressed to approximately 700′ west of 136th Avenue.
  • Pipe laying will continue with both crews next week. The 136th Avenue crossing is tentatively scheduled for July 20.
  • Work inside the pipe continues.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • Pipe laying is expected to resume near the end of July.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Work continued on various pipe appurtenances within New Holland Street.
  • Work in New Holland Street will continue next week in preparation for paving the week of July 27.
  • Van Buren Street from Butternut to 136th Avenue is closed.
  • Next week, Van Buren Street from 136th Avenue to US-31 will be closed and preparations for pipe laying will begin including road removal, installation of dewatering, and pipe staging.
  • Road building between 160th and 152nd continues. Paving for this length of road has been rescheduled for the week of July 13.
  • Pipe laying between 152nd and 144th Avenue has progressed to Pond Drive and will continue eastward next week.
  • Pipe laying between 144th and 136th Avenue has progressed halfway between 140th and 136th Avenue and will continue eastward next week.
  • Work inside the pipe continues.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • Pipe laying is expected to resume near the end of July.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Work continued on various pipe appurtenances within New Holland Street.
  • Valve vault and valve installation have been completed and the remaining pipe will be installed next week.
  • Work in New Holland Street will continue next week in preparation for paving.
  • Van Buren Street from Butternut to 136th Avenue is closed.
  • The intersection of 160th and Van Buren was reopened on June 13.
  • Road building between 160th and 152nd has begun. During road building, K&R will be performing spot excavations to seal off various pipeline appurtenances. Paving for this length of road is tentatively scheduled for the week of July 6.
  • Pipe laying between 152nd and 144th Avenue restarted approximately 500′ east of 152nd Avenue and is continuing eastward.
  • Pipe laying between 144th and 136th Avenue has progressed east of 140th Avenue and will continue eastward next week.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • Road building continues between US-31 and 128th Avenue.
  • Pipe laying is expected to resume near the end of July.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Work continued on various pipe appurtenances within New Holland Street.
  • Excavation for placement of the valve and valve vault north of New Holland Street began.
  • Valve vault and valve are expected to be installed next week. This is the last length of transmission main to be installed on Contract 3.
  • Van Buren Street from Butternut to 136th Avenue is closed.
  • The intersection of 160th and Van Buren is closed.
  • Installed large valve vault and appurtenances adjacent to the 160th intersection. Work near the intersection will continue this week and the intersection is tentatively scheduled to be paved on Saturday, June 13.
  • Near 144th, K&R’s second pipe crew has progressed approximately 1,400′ east of 144th and will continue east this week.
  • Work inside the pipeline continues.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • Some road building will be occurring between US-31 and 128th Avenue.
  • Work inside the pipeline continues.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Work continued on various pipe appurtenances at the south of end the work area and near the SW of Blendon Drain. Final restoration at the southern end of the easement began.
  • Work will continue generally progressing from south to north. This week, efforts will be focused on the valve vault south of New Holland Street and on continuing restoration.