November 21, 2025
- Van Buren Street from Butternut to 160th Avenue is closed. 160th to 152nd Avenue is tentatively scheduled to close the week of 12/1.
- K&R continued pipe laying in Van Buren Street and is progressing west to east. Pipe laying will continue next week.
- Van Buren Street from US-31 to 128th Avenue is closed.
- K&R continued pipe laying this week, progressing west to east. Pipe laying will continue next week. Pipe deliveries along Van Buren Street continue.
- Van Buren Street from 104th Avenue to 96th Avenue is closed.
- Ric-Man installed the 48″ x 60″ tee in Van Buren Street.
- Ric-Man received valve chambers components and is beginning valve chamber installation in Van Buren Street.
- New Holland Street from 104th Avenue to 96th Avenue is closed.
- Pipe deliveries continue on New Holland Street.
- Fabrication of the surge tanks for the Surge Suppression System is underway.