City of Wyoming - Water Transmission Main No. 3

Important Information

The City of Wyoming owns and operates the Donald K. Shine Drinking Water Plant located near Lake Michigan on New Holland Street. Water from Lake Michigan is pumped to the plant where it is treated and then distributed to thirteen communities serving over 250,000 people in Ottawa and Kent Counties.

The City and Ottawa County is embarking on a multi-year construction project to enhance this regional asset through construction of approximately 11 miles of pipeline. This project, funded by ratepayers from the customer communities, will improve the drinking water transmission system reliability and functionality for the entire region.

The project is expected to be completed over several years with multiple contractors coordinating their efforts. Kamminga & Roodvoets of Grand Rapids, Michigan and Ric-Man Construction of Sterling Heights, Michigan are the two general contractors entrusted to construct this pipeline.

A map depicting the project area and general schedule for the project can be viewed at the link below.

Access/Traffic:

Local traffic will be maintained during pipeline construction. There may be times when your driveway is inaccessible because pipeline construction is occurring in front of your house or driveway restoration is taking place. The contractor will work with you ahead of time and will make special access arrangements with you if needed.

Mail:

Mailboxes that interfere with pipeline construction will be temporarily relocated so that mail service can be maintained during construction. If your mailbox needs to be temporarily relocated, the contractor will inform you of where it has been moved to.

Garbage Pickup:

The contractor will work with you and your waste hauler to maintain service throughout construction. If pipeline construction interferes with your waste haulers ability to pick up your garbage, the contractor will temporarily move your garbage binds to a central location and return them to the end of your driveway by the end of the work day.

Contractor:

Kamminga & Roodvoets
Ric-Man Construction

City of Wyoming
waterprojects@wyomingmi.gov

K&R has spent the last several weeks excavating various pipe joints to correct some issues. Locations of the excavations change every couple of days and access around these excavations can be impossible. Today’s excavation is in front of 15975 Van Buren Street. Tomorrow, K&R will be excavating a joint in front of 15881 Van Buren Street.

  • Van Buren Street from Butternut to 160thAvenue is closed, from 160th to 152nd Avenue is closed, and from 152nd to 144th is closed.
  • Pipe laying has halted for the time being. K&R is continuing miscellaneous external and internal work on pipe already installed.
  • The first course of asphalt paving between Butternut and 160th Avenue is tentatively scheduled for the week of May 11, weather permitting. Restoration and road building along this length of road will begin soon as weather permits.

 

  • Van Buren Street from US-31 to 120thAvenue is closed.
  • Pipe laying continued eastward as weather conditions allowed. Pipe laying will continue next week as well as work inside the pipe.

 

  • New Holland Street from 104thAvenue to 96th Avenue is closed.
  • Ric-Man continues working on the pipe interior in preparation for pressure testing. Filling of the pipeline is expected to begin today.
  • Next week, Ric-Man will fill the remaining pipeline and pressure test, then begin connections to the existing pipeline in New Holland Street.
  • Van Buren Street from Butternut to 160thAvenue is closed, from 160th to 152nd Avenue is closed, and from 152nd to 144th is closed.
  • Pipe laying has progressed east of Quail Meadow Court.
  • Next week, K&R will continue laying pipe eastward toward 152nd Miscellaneous external and internal work on pipe already installed will continue.
  • Road building between Butternut and 160th Avenue is anticipated to begin shortly.

 

  • Van Buren Street from US-31 to 120thAvenue is closed.
  • Pipe laying crossed 124th Avenue and will continue eastward next week.

 

  • New Holland Street from 104thAvenue to 96th Avenue is closed.
  • Ric-Man completed the connection from the New Holland Street pipe to the easement pipe previously installed south of New Holland Street. They are working to finish the pipe interior and exterior in preparation for pressure testing.
  • Over the next few weeks, Ric-Man will fill the pipeline in New Holland Street and south of New Holland Street for pressure testing. After pressure testing, the new pipeline will be connected to the existing pipeline, disinfected and tested, and then returned to service.
  •  Van Buren Street from Butternut to 160thAvenue is closed, from 160th to 152nd Avenue is closed, and from 152nd to 144th is closed.
  •  K&R spent the first part of this week investigating joints west of their current work area and preparing the area between Butternut and 160th Avenue for road building.
  •  Pipe laying near Quail Meadow Court resumed yesterday and will continue eastward into next week.
  •  Joint repairs west of the current work area will continue this week and into next.
  •  Road building preparations will continue next week between Butternut and 160th Road building cannot begin until the joint repairs are completed.

 

  •  Van Buren Street from US-31 to 120thAvenue is closed.
  •  Pipe laying is very near to 124th K&R may still cross 124th Avenue this week, weather permitting. Pipe laying will continue next week.
  •  Work inside the pipe continues.
  •  The valve vault for the valve near 128th Avenue is scheduled to arrive this week. At some point, K&R will move back west to install the vault, valve, and adjacent piping. This work has not yet been scheduled.

 

  •  New Holland Street from 104thAvenue to 96th Avenue is closed. The open trench crossing the road has been backfilled and temporarily restored.
  •  Ric-Man installed the second gate valve south of New Holland Street.
  •  Ric-Man is currently excavating for placement of a valve vault south of New Holland Street. This work will continue into next week.
  • Van Buren Street from Butternut to 160thAvenue is closed, from 160th to 152nd Avenue is closed, and from 152nd to 144th is closed.
  • K&R spent most of this week preparing the area between Butternut and 160th Avenue for road building. Work included general site cleanup and miscellaneous external and internal pipe work.
  • Road building between Butternut and 160th Avenue is anticipated to begin shortly.
  • Next week, K&R may continue pipe laying through Quail Meadow Court, weather permitting.

 

  • Van Buren Street from US-31 to 120thAvenue is closed.
  • Pipe deliveries for work east of US-31 are complete.
  • Pipe laying is approaching 124th K&R plans to cross 124th Avenue this coming week, weather permitting.
  • Work inside the pipe continues.

 

  • New Holland Street from 104thAvenue to 96th Avenue is closed. The road is closed with an open trench across the street for pipe installation. The trench will be backfilled and the road open by end of Monday, 3/30.
  • Ric-Man is working on connections from the New Holland Street pipe to the easement piping previously installed. They installed one gate valve north of New Holland Street this week and are working on installation of a second gate valve south of New Holland Street.
  • One of two 42″ ball valves arrived on site this week.
  • Next week, Ric-Man will continue working on piping in this area, including installation of a valve vault south of New Holland Street.
  • Van Buren Street from Butternut to 160thAvenue is closed, from 160th to 152nd Avenue is closed, and from 152nd to 144th is closed.
  • Pavement was removed on the north side of Van Buren between 152nd and 144th. Preparations for pipe laying will continue next week.
  • Pipe laying continued between 160th and 152nd. Pipe work inside the pipe continues.
  • Next week, K&R will continue pipe laying through Quail Meadow Court and continuing east. They will also fall back to complete some outstanding work between Butternut and 160th.

 

  • Van Buren Street from US-31 to 120thAvenue is closed.
  • Pipe deliveries for work east of US-31 will be complete be the end of next week.
  • Pipe laying continues between 128th and 120th Pipe work inside the pipe continues.

 

  • New Holland Street from 104thAvenue to 96th Avenue is closed.
  • City of Wyoming completed an inspection of its existing 54″ transmission main either side of the project area.
  • This week, Ric-Man began making connections from the New Holland Street pipe to the easement piping previously installed. Connections will include installation of precast vaults, valving, and piping. This work will continue next week.

K&R will be closing Van Buren Street between 144th and 152nd starting today to begin preparations for pipe laying. Traffic will be detoured around the closure area via Port Sheldon Street. See detour route here.

Work will include pavement removal, staging of pipe along the road, dewatering, and some utility relocation. K&R has coordinated with the Post Office to set up a temporary mailbox bank at the NE corner of the 152nd Avenue and Van Buren Street intersection. A letter from K&R was mailed last week in advance of the closure providing more information.

  • Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
  • Van Buren Street from 152nd to 144th Avenue will be closed this week to begin preparations for pipe laying. The Contractor recently sent out a letter describing the anticipated work activities.
  • K&R is approaching Buck Fever Drive with pipeline installation. They should cross the drive first thing this week and continue progressing east from 160th.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • K&R continued laying pipe east of 128th Avenue. Next week, they will continue to lay pipe. Pipe laying is approximately 1,000’ east of 128th Avenue.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man completed initial pipe installation in New Holland Street last week. See attached photo of the last piece of existing pipe removed.
  • This week, Ric-Man will begin making connections from the New Holland Street pipe to the easement piping previously installed. Connections will include installation of precast vaults, valving, and piping.

MAP: Van Buren Detour 1B

  • Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
  • K&R crossed Martini Ln with pipeline this week.
  • K&R continues to lay pipe in Van Buren progressing east from 160th. They are approximately 600′ west of Buck Fever Drive.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • K&R continued laying pipe east of 128th Avenue. Next week, they will continue to lay pipe.
  • K&R has pipe staged to nearly 104th Avenue and will continue staging pipe along the remainder of the route.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man continued pipe installation in New Holland Street. They will complete initial pipe installation in New Holland Street next week.
  • Next week, Ric-Man will begin making connections from the New Holland Street pipe to the easement piping previously installed. Connections will include installation of precast vaults, valving, and piping.
  • Total pipe installed ~16,800 ft of 64,000 ft = ~26%

 

  • Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
  • K&R crossed Whitetail Ct with pipeline this week.
  • Approximately 4,000′ of pipe has been installed on this project.
  • K&R continues to lay pipe in Van Buren progressing east from 160th. They are approximately 400′ west of Whitetail Ct.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • K&R crossed 128th Avenue with pipeline this week and is restoring the intersection.
  • Approximately 3,800′ of pipe has been installed on this project.
  • Next week, K&R will continue to lay pipe in Van Buren progressing east. A small section of pipe just east of 128th Avenue will be skipped until additional materials arrive. This section of pipe will be installed later.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man continued pipe installation in New Holland Street. Approximately 900′ of pipe in New Holland Street remains to be installed.