City of Wyoming - Water Transmission Main No. 3

Important Information

The City of Wyoming owns and operates the Donald K. Shine Drinking Water Plant located near Lake Michigan on New Holland Street. Water from Lake Michigan is pumped to the plant where it is treated and then distributed to thirteen communities serving over 250,000 people in Ottawa and Kent Counties.

The City and Ottawa County is embarking on a multi-year construction project to enhance this regional asset through construction of approximately 11 miles of pipeline. This project, funded by ratepayers from the customer communities, will improve the drinking water transmission system reliability and functionality for the entire region.

The project is expected to be completed over several years with multiple contractors coordinating their efforts. Kamminga & Roodvoets of Grand Rapids, Michigan and Ric-Man Construction of Sterling Heights, Michigan are the two general contractors entrusted to construct this pipeline.

A map depicting the project area and general schedule for the project can be viewed at the link below.

Access/Traffic:

Local traffic will be maintained during pipeline construction. There may be times when your driveway is inaccessible because pipeline construction is occurring in front of your house or driveway restoration is taking place. The contractor will work with you ahead of time and will make special access arrangements with you if needed.

Mail:

Mailboxes that interfere with pipeline construction will be temporarily relocated so that mail service can be maintained during construction. If your mailbox needs to be temporarily relocated, the contractor will inform you of where it has been moved to.

Garbage Pickup:

The contractor will work with you and your waste hauler to maintain service throughout construction. If pipeline construction interferes with your waste haulers ability to pick up your garbage, the contractor will temporarily move your garbage binds to a central location and return them to the end of your driveway by the end of the work day.

Contractor:

Kamminga & Roodvoets
Ric-Man Construction

City of Wyoming
waterprojects@wyomingmi.gov

  • Van Buren Street from Butternut to 160thAvenue is closed, from 160th to 152nd Avenue is closed, and from 152nd to 144th is closed.
  • Pavement was removed on the north side of Van Buren between 152nd and 144th. Preparations for pipe laying will continue next week.
  • Pipe laying continued between 160th and 152nd. Pipe work inside the pipe continues.
  • Next week, K&R will continue pipe laying through Quail Meadow Court and continuing east. They will also fall back to complete some outstanding work between Butternut and 160th.

 

  • Van Buren Street from US-31 to 120thAvenue is closed.
  • Pipe deliveries for work east of US-31 will be complete be the end of next week.
  • Pipe laying continues between 128th and 120th Pipe work inside the pipe continues.

 

  • New Holland Street from 104thAvenue to 96th Avenue is closed.
  • City of Wyoming completed an inspection of its existing 54″ transmission main either side of the project area.
  • This week, Ric-Man began making connections from the New Holland Street pipe to the easement piping previously installed. Connections will include installation of precast vaults, valving, and piping. This work will continue next week.

K&R will be closing Van Buren Street between 144th and 152nd starting today to begin preparations for pipe laying. Traffic will be detoured around the closure area via Port Sheldon Street. See detour route here.

Work will include pavement removal, staging of pipe along the road, dewatering, and some utility relocation. K&R has coordinated with the Post Office to set up a temporary mailbox bank at the NE corner of the 152nd Avenue and Van Buren Street intersection. A letter from K&R was mailed last week in advance of the closure providing more information.

  • Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
  • Van Buren Street from 152nd to 144th Avenue will be closed this week to begin preparations for pipe laying. The Contractor recently sent out a letter describing the anticipated work activities.
  • K&R is approaching Buck Fever Drive with pipeline installation. They should cross the drive first thing this week and continue progressing east from 160th.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • K&R continued laying pipe east of 128th Avenue. Next week, they will continue to lay pipe. Pipe laying is approximately 1,000’ east of 128th Avenue.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man completed initial pipe installation in New Holland Street last week. See attached photo of the last piece of existing pipe removed.
  • This week, Ric-Man will begin making connections from the New Holland Street pipe to the easement piping previously installed. Connections will include installation of precast vaults, valving, and piping.

MAP: Van Buren Detour 1B

  • Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
  • K&R crossed Martini Ln with pipeline this week.
  • K&R continues to lay pipe in Van Buren progressing east from 160th. They are approximately 600′ west of Buck Fever Drive.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • K&R continued laying pipe east of 128th Avenue. Next week, they will continue to lay pipe.
  • K&R has pipe staged to nearly 104th Avenue and will continue staging pipe along the remainder of the route.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man continued pipe installation in New Holland Street. They will complete initial pipe installation in New Holland Street next week.
  • Next week, Ric-Man will begin making connections from the New Holland Street pipe to the easement piping previously installed. Connections will include installation of precast vaults, valving, and piping.
  • Total pipe installed ~16,800 ft of 64,000 ft = ~26%

 

  • Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
  • K&R crossed Whitetail Ct with pipeline this week.
  • Approximately 4,000′ of pipe has been installed on this project.
  • K&R continues to lay pipe in Van Buren progressing east from 160th. They are approximately 400′ west of Whitetail Ct.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • K&R crossed 128th Avenue with pipeline this week and is restoring the intersection.
  • Approximately 3,800′ of pipe has been installed on this project.
  • Next week, K&R will continue to lay pipe in Van Buren progressing east. A small section of pipe just east of 128th Avenue will be skipped until additional materials arrive. This section of pipe will be installed later.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man continued pipe installation in New Holland Street. Approximately 900′ of pipe in New Holland Street remains to be installed.
  • Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
  • K&R continues to lay pipe in Van Buren progressing east from 160th. They are approximately 400′ west of Whitetail Ct.
  • Van Buren Street from US-31 to 128th Avenue is closed.
  • Van Buren Street from 128th to 120th is scheduled to close next week.
  • K&R continues to lay pipe in Van Buren progressing east. They anticipate crossing 128th Avenue next week. The intersection crossing will take a few days to complete.
  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man installed two valve vaults and vault piping. Next week they will continue laying pipe progressing east toward 96th Avenue.
  • Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
  • After many weather delays, K&R began laying pipe again this week east of 160th Avenue progressing from west to east.

 

  • Van Buren Street from US-31 to 128th Avenue is closed.
  • K&R has had a couple weeks of pipe laying production. They are approximately halfway between 132nd Avenue and 128th Avenue with pipe laying.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man has approximately half of the transmission main removal and replacement in New Holland Street complete. Ric-Man will be installed valve vaults next week.
  • Work in New Holland Street has been much slower than anticipated and is likely to continue into early Spring.
  • Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
  • This week, K&R performed joint work within the pipeline. Next week, K&R will start dewatering between 160th and 152nd Avenue in preparation for pipe laying the week of 1/19, otherwise there will not a lot of activity on-site.

 

  • Van Buren Street from US-31 to 128th Avenue is closed.
  • K&R resumed pipe laying this week, progressing west to east. Next week, there will not be a lot of activity on-site. Pipe laying will resume the week of 1/19.

 

  • Van Buren Street from 104th Avenue to 96th Avenue has been reopened.
  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man has begun removal and replacement of transmission main in New Holland Street, progressing west to east. Work is expected to continue for several weeks.

 

  • Excavation for the surge tank building foundation is anticipated to resume next week.

Monday, December 15, 2025

  • Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
  • Last week, K&R installed blowoff piping near the Munn Drain. Pipe laying will continue this week and reach the west side of the 160th Avenue intersection.
  • Van Buren Street from US-31 to 128th Avenue is closed.
  • K&R continued pipe laying last week, progressing west to east. Pipe laying will continue this week east of 132nd Avenue.
  • The contractor will be shutting down the Van Buren jobsites over the holidays. Prior to the showdown, the jobsite will be cleaned up for local traffic. Snow plowing will continue through the holidays.

 

  • Van Buren Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man installed two valve vaults in Van Buren Street. Van Buren Street will be restored and opened to traffic this week.
  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • City of Wyoming isolated and drained the existing Transmission Main in New Holland Street.
  • Ric-Man will cut into the Transmission Main in New Holland Street and begin pipe replacement.

 

  • Excavation for the surge tank building foundation began. Excavation and densification efforts will continue this week.
  • Van Buren Street from Butternut to 160th Avenue is closed. 160th to 152nd Avenue is scheduled to close next week.
  • K&R continued pipe laying in Van Buren Street and is progressing west to east. Pipe laying will continue next week. Approximately 1,800′ of pipe has been installed within this stretch.
  • Van Buren Street from US-31 to 128th Avenue is closed.
  • K&R continued pipe laying this week, progressing west to east. Pipe laying will continue next week. Approximately 300′ of pipe has been installed within this stretch.
  • Van Buren Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man installed the first valve vault of the project. Vault installation will continue next week.
  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Pipe deliveries finished on New Holland Street.
  • Excavation for the surge tank building foundation will tentatively begin next week.