The City of Wyoming owns and operates the Donald K. Shine Drinking Water Plant located near Lake Michigan on New Holland Street. Water from Lake Michigan is pumped to the plant where it is treated and then distributed to thirteen communities serving over 250,000 people in Ottawa and Kent Counties.

The City and Ottawa County is embarking on a multi-year construction project to enhance this regional asset through construction of approximately 11 miles of pipeline. This project, funded by ratepayers from the customer communities, will improve the drinking water transmission system reliability and functionality for the entire region.

The project is expected to be completed over several years with multiple contractors coordinating their efforts. Kamminga & Roodvoets of Grand Rapids, Michigan and Ric-Man Construction of Sterling Heights, Michigan are the two general contractors entrusted to construct this pipeline.

A map depicting the project area and general schedule for the project can be viewed at the link below.

Access/Traffic:

Local traffic will be maintained during pipeline construction. There may be times when your driveway is inaccessible because pipeline construction is occurring in front of your house or driveway restoration is taking place. The contractor will work with you ahead of time and will make special access arrangements with you if needed.

Mail:

Mailboxes that interfere with pipeline construction will be temporarily relocated so that mail service can be maintained during construction. If your mailbox needs to be temporarily relocated, the contractor will inform you of where it has been moved to.

Garbage Pickup:

The contractor will work with you and your waste hauler to maintain service throughout construction. If pipeline construction interferes with your waste haulers ability to pick up your garbage, the contractor will temporarily move your garbage binds to a central location and return them to the end of your driveway by the end of the work day.

Contractor:

Kamminga & Roodvoets
Ric-Man Construction

City of Wyoming
waterprojects@wyomingmi.gov

  • Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
  • K&R continues to lay pipe in Van Buren progressing east from 160th. They are approximately 400′ west of Whitetail Ct.
  • Van Buren Street from US-31 to 128th Avenue is closed.
  • Van Buren Street from 128th to 120th is scheduled to close next week.
  • K&R continues to lay pipe in Van Buren progressing east. They anticipate crossing 128th Avenue next week. The intersection crossing will take a few days to complete.
  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man installed two valve vaults and vault piping. Next week they will continue laying pipe progressing east toward 96th Avenue.
  • Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
  • After many weather delays, K&R began laying pipe again this week east of 160th Avenue progressing from west to east.

 

  • Van Buren Street from US-31 to 128th Avenue is closed.
  • K&R has had a couple weeks of pipe laying production. They are approximately halfway between 132nd Avenue and 128th Avenue with pipe laying.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man has approximately half of the transmission main removal and replacement in New Holland Street complete. Ric-Man will be installed valve vaults next week.
  • Work in New Holland Street has been much slower than anticipated and is likely to continue into early Spring.
  • Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
  • This week, K&R performed joint work within the pipeline. Next week, K&R will start dewatering between 160th and 152nd Avenue in preparation for pipe laying the week of 1/19, otherwise there will not a lot of activity on-site.

 

  • Van Buren Street from US-31 to 128th Avenue is closed.
  • K&R resumed pipe laying this week, progressing west to east. Next week, there will not be a lot of activity on-site. Pipe laying will resume the week of 1/19.

 

  • Van Buren Street from 104th Avenue to 96th Avenue has been reopened.
  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man has begun removal and replacement of transmission main in New Holland Street, progressing west to east. Work is expected to continue for several weeks.

 

  • Excavation for the surge tank building foundation is anticipated to resume next week.

Monday, December 15, 2025

  • Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
  • Last week, K&R installed blowoff piping near the Munn Drain. Pipe laying will continue this week and reach the west side of the 160th Avenue intersection.
  • Van Buren Street from US-31 to 128th Avenue is closed.
  • K&R continued pipe laying last week, progressing west to east. Pipe laying will continue this week east of 132nd Avenue.
  • The contractor will be shutting down the Van Buren jobsites over the holidays. Prior to the showdown, the jobsite will be cleaned up for local traffic. Snow plowing will continue through the holidays.

 

  • Van Buren Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man installed two valve vaults in Van Buren Street. Van Buren Street will be restored and opened to traffic this week.
  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • City of Wyoming isolated and drained the existing Transmission Main in New Holland Street.
  • Ric-Man will cut into the Transmission Main in New Holland Street and begin pipe replacement.

 

  • Excavation for the surge tank building foundation began. Excavation and densification efforts will continue this week.
  • Van Buren Street from Butternut to 160th Avenue is closed. 160th to 152nd Avenue is scheduled to close next week.
  • K&R continued pipe laying in Van Buren Street and is progressing west to east. Pipe laying will continue next week. Approximately 1,800′ of pipe has been installed within this stretch.
  • Van Buren Street from US-31 to 128th Avenue is closed.
  • K&R continued pipe laying this week, progressing west to east. Pipe laying will continue next week. Approximately 300′ of pipe has been installed within this stretch.
  • Van Buren Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man installed the first valve vault of the project. Vault installation will continue next week.
  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Pipe deliveries finished on New Holland Street.
  • Excavation for the surge tank building foundation will tentatively begin next week.
  • Van Buren Street from Butternut to 160th Avenue is closed. 160th to 152nd Avenue is tentatively scheduled to close the week of 12/1.
  • K&R continued pipe laying in Van Buren Street and is progressing west to east. Pipe laying will continue next week.
  • Van Buren Street from US-31 to 128th Avenue is closed.
  • K&R continued pipe laying this week, progressing west to east. Pipe laying will continue next week. Pipe deliveries along Van Buren Street continue.
  • Van Buren Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man installed the 48″ x 60″ tee in Van Buren Street.
  • Ric-Man received valve chambers components and is beginning valve chamber installation in Van Buren Street.
  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Pipe deliveries continue on New Holland Street.
  • Fabrication of the surge tanks for the Surge Suppression System is underway.
  • Van Buren Street from Butternut to 160th Avenue is closed.
  • K&R continued pipe laying in Van Buren Street and is progressing west to east. Pipe laying will continue next week.
  • Van Buren Street from US-31 to 128th Avenue is closed.
  • K&R began pipe laying this week, progressing west to east. Pipe laying will continue next week.
  • Van Buren Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man began laying pipe in Van Buren Street today. They will be receiving valve chambers and will continue with transmission main and valve chamber placement in Van Buren Street.
  • New Holland Street from 104th Avenue to 96th Avenue was closed this week and will remain closed through the winter. The closed road section will be cleared and maintained for local, non-thru traffic during winter weather.
  • New Holland Street was pulverized within the closed length and pipe deliveries began. 42″ gate valves and 60″ butterfly valves were delivered to the site.
  • Next week at the DWP, OAK will continue excavation for the surge tank building foundation.
  • The project was featured in a woodtv8 segment, linked here: https://www.woodtv.com/news/kent-county/wyoming-says-10-miles-of-new-water-line-will-support-community-for-decades/

  • Van Buren Street from Butternut to 160th Avenue is closed.
  • K&R resumed pipe laying in Van Buren Street and is progressing west to east.
  • Van Buren Street from US-31 to 128th Avenue is closed.
  • Pipe and equipment deliveries began last week. K&R is scheduled to begin pipe laying this week, progressing west to east.
  • Van Buren Street from 104th Avenue to 96th Avenue was closed today.
  • Ric-Man is approaching Van Buren Street with pipe laying and will begin laying in the road soon.
  • New Holland Street from 104th Avenue to 96th Avenue is scheduled to close 11/12 and will remain closed through the winter. The closed road section will be cleared and maintained for local, non-thru traffic during winter weather.
  • Road pulverization and pipe and equipment deliveries along the closed length of New Holland Street will begin soon.
  • Excavation began at the Drinking Water Plant for the surge tank building foundation.

Last week: 

  • Ric-Man resumed pipe laying between Barry Street and Van Buren Street.
  • Tree clearing for surge suppression improvements continued at the Wyoming Drinking Water Plant.

Coming up:

  • K&R is planning to mobilize a second crew the week of November 3. The second crew will begin work east of US-31 on Van Buren Street. Pipe laying is scheduled to begin the week of November 10.

Closures: 

  • Van Buren Street from Butternut to 160th Avenue remains closed. K&R is planning to re-mobilize and resume pipe laying within this area the week of November 3.
  • New Holland Street between 96th Avenue and 104th Avenue is tentatively scheduled to close on November 3 for the foreseeable future. The detour will be via Quincy Street.
  • Van Buren Street from US-31 to 128th Avenue is scheduled to close on November 3. The detour will be via New Holland Street.

Ric-Man has temporarily stopped pipe laying and is beginning initial restoration efforts at the southern end of the project. Pipe laying is anticipated to resume near the end of October. In the meantime, Ric-Man will continue initial restoration efforts, and begin installing pipe appurtenances (valves, air valves, hydrants) and completing work within the pipe interior.

Van Buren Street from Butternut to 160th Avenue remains closed. Pipe from Butternut to 160th Avenue has been delivered and staged along Van Buren Street.

K&R’s pipe laying has been delayed to the start of November.