This project is designed to control the lake levels of Eagle Lake and Crooked Lake by means of two lakebed intake beds, two pumping stations, 3,724 linear feet of force main, and a filter building with mechanical filters.
Tentative Project Schedule:
There will be times in the spring of 2024 where residents along West PQ Avenue and the easterly end of West Crooked Lake Drive will have the area in front of your homes torn up. You will have limited access to your home for a very brief period of possibly several hours. Please let us know if you have any special access needs and we will do our best to make arrangements with you.
Contact any project representative if you have questions or concerns. Thank you for your patience and we look forward to a successful project in your area!
Prein&Newhof will have personnel in the field on behalf of the Charter Township of Texas.
Tom Wheat, PE
Project Manager
(269) 372-1158
Janine DeVries
Onsite Contact
(616) 450-9854
Dennis Todd
Onsite Contact
(269) 615-2906
_________________________________
Charter Township of Texas
Erik Wilson
(269) 375-1591
Kalamazoo County Drain Commissioner
Jason Wiersma
(269) 384-8117
_________________________________
Contractor: Balkema Excavating
Kyle Batts
24-Hour Emergency Contact
(269) 998-6508
Infiltration piping has been installed and sand backfilling has been completed at Eagle Lake. Please continue to be alert for construction vehicles.
Upcoming Schedule:
Precast planks have been placed at the filter building. Dredging was completed yesterday at Eagle Lake. The dredging contractor will place sand for the infiltration system. Please continue to be alert for construction vehicles.
Upcoming Schedule:
Dredging in Crooked Lake is complete. The Crooked Lake ramp is open for boat traffic. The contractor is working on final touch-ups at the ramp.
Upcoming Schedule:
The dredging crew plans to finish sand backfilling in Crooked Lake this week. Thank you for your patience as the Crooked Lake ramp will be unable to accommodate boat traffic during the transportation of sand for backfilling.