This project is designed to control the lake levels of Eagle Lake and Crooked Lake by means of two lakebed intake beds, two pumping stations, 3,724 linear feet of force main, and a filter building with mechanical filters.
Tentative Project Schedule:
There will be times in the spring of 2024 where residents along West PQ Avenue and the easterly end of West Crooked Lake Drive will have the area in front of your homes torn up. You will have limited access to your home for a very brief period of possibly several hours. Please let us know if you have any special access needs and we will do our best to make arrangements with you.
Contact any project representative if you have questions or concerns. Thank you for your patience and we look forward to a successful project in your area!
_________________________________
Prein&Newhof will have personnel in the field on behalf of the Charter Township of Texas.
Tom Wheat, PE
Project Manager
(269) 372-1158
Janine DeVries
Onsite Contact
(616) 450-9854
Dennis Todd
Onsite Contact
(269) 615-2906
_________________________________
Charter Township of Texas
Erik Wilson
(269) 375-1591
Kalamazoo County Drain Commissioner
Jason Wiersma
(269) 384-8117
_________________________________
Contractor: Balkema Excavating
Kyle Batts
24-Hour Emergency Contact
(269) 998-6508
Horizontal Directional Drilling (HDD) of pipe at the east end of Crooked Lake has been completed.
Upcoming Schedule:
Horizontal Directional Drilling (HDD) of pipe at the east end of Crooked Lake has begun. Last week, pipe was installed from Crooked Lake to the proposed filter station.
This week, they anticipate installing the 12-inch pipe from the filter station to the outlet point:
Horizontal Directional Drilling (HDD) of pipe at the east end of Crooked Lake has begun. Last week, the drilling subcontractor set up on-site to begin directional drilling from Crooked Lake to the proposed filter station.
This week, they anticipate installing the 12-inch pipe:
Thank you for your patience as the Crooked Lake ramp will be used for about 15 minutes sometime between 7-9am on Friday, September 15 to float the pipe onto the lake and to the project site. The pipe will continue to be floated on Friday until it is fully installed. The contractor will properly flag and monitor its location to ensure no conflicts with boating traffic.
The contract was awarded to Balkema Excavating, and they are busy preparing and submitting shop drawings for the project. Shop drawings are a means by which we can confirm that the contractor will be providing the proper materials and equipment specified in the contract.
Upcoming Schedule: