City of Wyoming - Water Transmission Main No. 3

Important Information

The City of Wyoming owns and operates the Donald K. Shine Drinking Water Plant located near Lake Michigan on New Holland Street. Water from Lake Michigan is pumped to the plant where it is treated and then distributed to thirteen communities serving over 250,000 people in Ottawa and Kent Counties.

The City and Ottawa County is embarking on a multi-year construction project to enhance this regional asset through construction of approximately 11 miles of pipeline. This project, funded by ratepayers from the customer communities, will improve the drinking water transmission system reliability and functionality for the entire region.

The project is expected to be completed over several years with multiple contractors coordinating their efforts. Kamminga & Roodvoets of Grand Rapids, Michigan and Ric-Man Construction of Sterling Heights, Michigan are the two general contractors entrusted to construct this pipeline.

A map depicting the project area and general schedule for the project can be viewed at the link below.

Access/Traffic:

Local traffic will be maintained during pipeline construction. There may be times when your driveway is inaccessible because pipeline construction is occurring in front of your house or driveway restoration is taking place. The contractor will work with you ahead of time and will make special access arrangements with you if needed.

Mail:

Mailboxes that interfere with pipeline construction will be temporarily relocated so that mail service can be maintained during construction. If your mailbox needs to be temporarily relocated, the contractor will inform you of where it has been moved to.

Garbage Pickup:

The contractor will work with you and your waste hauler to maintain service throughout construction. If pipeline construction interferes with your waste haulers ability to pick up your garbage, the contractor will temporarily move your garbage binds to a central location and return them to the end of your driveway by the end of the work day.

Contractor:

Kamminga & Roodvoets
Ric-Man Construction

City of Wyoming
waterprojects@wyomingmi.gov

Van Buren – Butternut to US-31

  • Van Buren from Butternut to US-31 is open to traffic.
  • The restoration crew has been preparing the area for winter and addressing some punchlist items.

 

164th Ave – New Holland to Van Buren

  • 164th Ave is closed between New Holland and Van Buren.

 

  • 164th Avenue has been paved. Pavement striping is scheduled for next week.
  • Restoration continues on 164th Avenue.

 

Van Buren – US-31 to 96th Ave

  • Van Buren from US-31 to 96th Ave is closed.
  • The intersection of Van Buren and 112th Ave was paved and reopened.
  • The intersection of Van Buren and 104th Ave has been closed.

 

  • One pipeline crew is building transmission main between 116th Ave and 112th Avenue.
  • A second pipeline crew built transmission main through 104th Avenue. The crew will continue eastward next week.
  • Road building continues west of the transmission main installation.

 

Easement

  • Site cleanup and punch list work will continue next week.

 

Drinking Water Plant – Surge Suppression System

  • Remaining building footings and foundation walls were poured
  • Lower level concrete pipe and valve supports will be poured
  • Foundation walls will be dampproofed, insulated, and backfilled

Van Buren – Butternut to US-31

  • Van Buren from Butternut to 160th Ave is closed.
  • Van Buren from 160th Ave to US-31 will be reopened to traffic by the end of the day.
  • The intersection of Van Buren, Butternut, and 164th Ave is closed.

 

  • The restoration crew has been preparing the area for winter and addressing some punchlist items.
  • The Butternut intersection was prepped for paving. Paving is tentatively scheduled for next week 11/9 and 11/12.

 

164th Ave – New Holland to Van Buren

  • 164th Ave is closed between New Holland and Van Buren.

 

  • Restoration and road building continued on 164th Avenue. Paving is tentatively scheduled for next week 11/9, 11/10, and 11/12.

 

Van Buren – US-31 to 96th Ave

  • Van Buren from US-31 to 96th Ave is closed.
  • The intersection of Van Buren and 112th Ave remains closed.

 

  • Transmission main installation crossed 112th Avenue. Next week, the pipeline crew will move west and begin laying the remaining transmission main between 120th Ave and 112th Avenue.
  • A second pipeline crew began building transmission main east of 108th Ave toward 104th Avenue. The 104th Ave intersection will be closed after the 112th Ave intersection is reopened.
  • Road building continued between 124th Ave and 120th Avenue.
  • The 112th Ave intersection is tentatively scheduled to be paved on 11/10.
  • Work inside the pipeline continues.
  • A large box culvert was installed between 104th Ave and 96th Avenue.

 

Easement

  • Acceptance testing of the transmission main is completed.
  • Restoration work within the Bosch & Hulst Drain continued and is expected to finish next week.
  • Site cleanup and punch list work will continue next week.

 

Drinking Water Plant – Surge Suppression System

  • Backfilling continued
  • The first section of Operating Level footings were poured and stripped. The remaining footings were formed and will be poured today.
  • Next, the Operating Level foundation walls will be prepped and poured.

Friday, October 30, 2026

 

Van Buren – Butternut to US-31

  • Van Buren from Butternut to US-31 is closed.
  • **The intersection of Van Buren, Butternut, and 164th is closed.**

 

  • The connection between the 164th Avenue and Van Buren Street transmission main was completed.
  • The pipeline crew will be moving east of US-31.
  • Work inside the pipeline will continue through next week as the intersection is prepared for paving.
  • Paving is scheduled for the week of November 9.

 

164th – New Holland to Van Buren

  • 164th Ave is closed between New Holland and Van Buren.

 

  • Work inside the pipeline will continue through next week as the road is prepared for paving.
  • Road building along 164th Avenue continued this week. Paving is tentatively scheduled for the week of November 9.

 

Van Buren – US-31 to 96th Avenue

  • Van Buren from US-31 to 104th Ave is closed.
  • The intersection of Van Buren and 112th Ave was closed yesterday and will remain closed for approximately three weeks.

 

  • Transmission main installation continues across 112th Avenue. After crossing 112th, the pipeline crew will move west and complete the remaining transmission main between 120th and 112th.
  • A second transmission main crew will mobilize next week and begin building transmission main east of 108th toward 104th.
  • Road building continued between 124th and 120th.
  • Work inside the pipeline continues.

 

New Holland – 104th to 96th & Easement

  • Van Buren Street between 104th and 96th Avenue is closed.

 

  • Acceptance testing is underway and will continue through the weekend.
  • Restoration work within the SW of Blendon Drain was completed.
  • Restoration work within the Bosch & Hulst Drains began and is expected to finish next week.

 

Drinking Water Plant – Surge Suppression System

  • Lower-level exterior surfaces have been damp proofed and insulated.
  • The site has been partially backfilled around the north, east, and west walls.
  • Forms and reinforcing have been installed for partial foundation wall footings, which are scheduled to be poured next week.

Remaining footing work and backfill to follow.

Van Buren – Butternut to US-31

  • Van Buren from Butternut to US-31 is closed.
  • **The intersection of Van Buren, Butternut, and 164th is closed.**

 

  • The final layer of asphalt from 144th to east of 136th has been paved.
  • Temporary asphalt was placed on Van Buren near US-31 where the tunneling work was suspended.
  • Pavement markings were placed.
  • The restoration crew continues to rebuild ditches; replace mailboxes; and topsoil, seed, and mulch areas disturbed by construction.

 

164th – New Holland to Van Buren

  • 164th Ave is closed between New Holland and Van Buren.

 

  • Transmission main installation in 164th Avenue has reached Butternut. The Butternut crossing will take place today through early next week. Paving is tentatively scheduled for the week of November 9.
  • Welding and joint grouting inside the pipe along 164th Ave pipeline continued this week.
  • Road building along 164th Avenue began this week. Paving is tentatively scheduled for the week of November 9.

 

Van Buren – US-31 to 96th Avenue

  • Van Buren from US-31 to 112th Ave is closed.
  • The intersection of Van Buren and 112th Ave is scheduled to close in the coming weeks.

 

  • Transmission main installation continues easterly and is approaching 112th Avenue.
  • Road building continues intermittently.

 

New Holland – 104th to 96th & Easement

  • Van Buren Street between 104th and 96th Avenue is closed.

 

  • Acceptance testing is underway and will continue next week.
  • Restoration work within the SW of Blendon Drain was completed.
  • Restoration work within the Bosch & Hulst Drainsis expected to begin this week.

 

Drinking Water Plant – Surge Suppression System

  • Basement slab and walls have been poured and forms removed.
  • Exterior surface has been prepped and damp proofing is underway.

Van Buren – Butternut to US-31

  • Van Buren from Butternut to US-31 is closed.
  • **The intersection of Van Buren, Butternut, and 164th is tentatively scheduled to close October 19.**

 

  • The final layer of asphalt from 144th to east of 136th is scheduled to be paved this week.
  • The restoration crew continues to rebuild ditches and seed areas disturbed by construction.

 

164th – New Holland to Van Buren

  • 164th Ave is closed between New Holland and Van Buren.

 

  • Transmission main installation continues. Approximately 4,000’ of TM has been installed in 164th Avenue and approximately 1,000′ remains.
  • Welding inside the pipe along 164th Ave pipeline will begin this week.

 

Van Buren – US-31 to 96th Avenue

  • Van Buren from US-31 to 112th Ave is closed.

 

  • Road building continues intermittently.

 

  • Transmission main installation continues east of 120th Avenue.
  • The tunneling operation beneath US-31 has been suspended for the time being.

 

New Holland – 104th to 96th & Easement

  • Van Buren Street between 104th and 96th Avenue is closed.

 

  • Acceptance testing is underway.
  • Restoration work within the SW of Blendon and Bosch & Hulst Drains is expected to begin this week.

 

Van Buren – Butternut to US-31

  • Van Buren from Butternut to US-31 is closed.

 

  • The first layer of asphalt has been paved from 140th through to west of US-31
  • The final layer of asphalt has been paved from 152nd to 144th.
  • The restoration crew continues to rebuild ditches between 144th and 136th. West of 144th has been seeded.

 

  • There will be some excavation work this week near 140th Avenue to locate and seal up an access point to the transmission main.

 

164th – New Holland to Van Buren

  • 164th Ave is closed between New Holland and Van Buren.

 

  • Transmission main installation continues. Approximately 3,000’ of TM has been installed in 164th Avenue and approximately 2,000′ remains.
  • Welding inside the pipe along 164th Ave pipeline will begin this week.

 

Van Buren – US-31 to 96th Avenue

  • Van Buren from US-31 to 112th Ave is closed.
  • The Van Buren/120th Avenue intersection was paved and re-opened over the weekend.

 

  • Road building between 128th and 124th is mostly completed.
  • Road building between 124th and 120th has begun.

 

  • Transmission main installation has progressed to approximately 900′ east of 120th Avenue and is continuing eastward.
  • The tunneling operation beneath US-31 has been suspended for the time being.

 

New Holland – 104th to 96th & Easement

  • Van Buren Street between 104th and 96th Avenue is closed.

 

  • Work continued on pipe appurtenances adjacent to Van Buren Street and Barry Street.
  • The transmission main has been filled and acceptance testing is underway.
  • Restoration work within the SW of Blendon and Bosch & Hulst Drains is expected to begin this week.

Van Buren – Butternut to US-31

  • Van Buren from Butternut to US-31 is closed.

 

  • Road building between 140th and 136th continued. Paving has been rescheduled to September 22 from 140th through 136th Ave.
  • Restoration between 152nd and 144th continues. Next week, the area will be seeded.

164th – New Holland to Van Buren

  • 164th Ave is closed between New Holland and Van Buren.

 

  • Transmission main installation began on the south end of 164th Avenue, progressing north. Approximately 800 feet of pipe was installed this week.

Van Buren – US-31 to 96th Avenue

  • Van Buren from US-31 to 120th Ave is closed.
  • The Van Buren/120th Avenue intersection was closed today and will stay closed for approximately two weeks.

 

  • The tunneling operation beneath US-31 has been suspended for the time being.
  • Transmission main installation began just west of 120th Avenue. The 120th Avenue crossing will take place Monday, September 21.

New Holland – 104th to 96th & Easement

  • Van Buren Street between 104th and 96th Avenue is closed.

 

  • Pavement striping and mailbox replacement was completed in New Holland Street.
  • Work continued on pipe appurtenances adjacent to Van Buren Street and Barry Street.
  • Next week, preparations for final acceptance testing will continue and the pipe will be filled. Acceptance testing is scheduled for late next week and the following week.

Van Buren – Butternut to US-31

  • Van Buren from Butternut to US-31 is closed.

 

  • Road building between 140th and 136th continues. Next week, the first layer of asphalt will be placed from 140th through 136th Ave.
  • Restoration between 152nd and 144th continues.

 

  • Work on miscellaneous transmission main items continued.
  • A repair to the transmission main near 140th Avenue was completed.
  • Work inside the pipe continues.

 

164th – New Holland to Van Buren

  • 164th Ave is closed between New Holland and Van Buren.

 

  • Unsuitable soils were removed from the work area in advance of transmission main installation.
  • Transmission main installation will begin first thing next week on the south end of 164th Avenue.

 

Van Buren – US-31 to 96th Avenue

  • Van Buren from US-31 to 120th Ave is closed.
  • The Van Buren/120th Avenue intersection is scheduled to close late next week for approximately two weeks.

 

  • The tunneling operation beneath US-31 has been suspended for the time being.
  • Work was completed on valve vault piping and adjacent appurtenances near 128th Avenue.
  • Transmission main installation will begin first thing next week just west of 120th Avenue, progressing east.

 

New Holland – 104th to 96th & Easement

  • Van Buren Street between 104th and 96th Avenue is closed.

 

  • Work continued on pipe appurtenances adjacent to Van Buren Street.
  • Next week, the interior of the pipe will be prepared for final acceptance testing. Acceptance testing is scheduled for the weeks of September 21 and 28.

 

Drinking Water Plant – Surge Suppression System

  • Basement plumbing passed air testing.
  • Basement slab rebar installation is underway.

Van Buren – Butternut to US-31

Van Buren from Butternut to US-31 is closed.

  • Road building between 140th and 136th continues.
  • Restoration between 152nd and 144th began.
  • Work on miscellaneous transmission main items continued.
  • Next week there will be an excavation near 140th Avenue to make a repair to the transmission main.
  • Work inside the pipe continues.

164th – New Holland to Van Buren

164th Ave is closed between New Holland and Van Buren.

  • A haul road was constructed this week to aid in transmission main installation.
  • Transmission main installation will begin later next week.

Van Buren – US-31 to 96th Avenue

Van Buren from US-31 to 120th Ave is closed.

  • The tunneling operation beneath US-31 has been suspended for the time being.
  • Work continued on valve vault piping and work on adjacent appurtenances near 128th Avenue. This work is nearly complete.
  • Next week, the pipe crew will begin pipe installation near 120th Avenue.

New Holland – 104th to 96th & Easement

Van Buren Street between 104th and 96th Avenue is closed.

  • Work continued on pipe appurtenances adjacent to Van Buren Street.
  • Next week, work will continue in Van Buren Street.
  • The interior of the pipe is being prepared for final acceptance testing.

Drinking Water Plant – Surge Suppression System

  • The sump has been constructed.
  • Basement plumbing has been installed and encased in concrete.
  • A mud mat was placed.
  • Next week, work on the basement slab will continue.

 

Van Buren – Butternut to US-31

  • Van Buren from Butternut to US-31 is closed.
  • The final layer of asphalt on driveways between Butternut and 152nd was placed.
  • The final layer of asphalt between Butternut and 152nd was placed this week. There is approximately 600′ of road near Butternut that will be completed later.
  • The initial layer of asphalt between 152nd and 140th was placed this week.
  • Road building between 140th and 136th began and will continue next week.
  • Work on miscellaneous transmission main items continued and will continue next week.
  • Work inside the pipe continues.

 

164th – New Holland to Van Buren

  • 164th Ave is closed between New Holland and Van Buren.
  • Pipe staging was completed this week.

 

Van Buren – US-31 to 96th Avenue

  • Van Buren from US-31 to 120th Ave is closed.
  • Work continued on valve vault piping and work on adjacent appurtenances near 128th Avenue. This work will continue next week.
  • Pipe crew may begin pipe installation west of 120th Avenue later next week.

 

New Holland – 104th to 96th & Easement

  • New Holland Street from 104th Ave to 96th Ave has been restored and is open to traffic.
  • Van Buren Street between 104th and 96th Avenue is tentatively scheduled to close on Monday (8/31).
  • Work continued on pipe appurtenances along Barry Street. A hydrant and air valve vault were installed.
  • Work began on pipe appurtenances just south of Van Buren Street.